What is the cement and sand consuption of 1:4 block work
Answer Posted / rakesh
cement part = 1/5, sand part = 4/5
now 1m3 of cement weighs 1440 kg and cube contains only 1/5part of it as cement. therefore, 1/5* 1440 kg cement present . and rest as sand..i.e. 1440*4/5kg
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
what is Brick crushing strength(PSI)?
howto calculate the quantities of material used in fly ash brick after finding the volume??
How to calculate Volume of Wet cement concrete for a specific grade?
How many types of slabs are there & how to design it?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
In cement making,what is meaning of blend,fineness,density.
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
What is OSHA compliance?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
explain five benefits of using standard terminology in the measurement process?
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
Material calculation of cm 1:6 for 1sqm
what is the mode of method of face bar measurement
what is the formula to find the diagonal shape stirrups?