how do we calculate the quantity cement,sand, & aggregate
for M20,M15 for 10cum.
Answers were Sorted based on User's Feedback
Answer / piyush singh
DIRECT ESTIMATION METHOD : =
M20 (1:1.5:3) for 10 m^3
1. cement content = 15.2 \ (1+1.5+3)
= 2.763 cum
= 82 bags of 50 kg
2. water = 2.763 cum * 1.5
3. ca + fa = 2.763 * 3 cum
* here 15.2 is a standard value worked out from experiments.
so for 10 m^3 u can divide the sum of ratio by 15.2 to get
amount of cement directly...
* 50 kg of cement (1 bag) = (1/30) m^3 so = 0.034 cum
2.763cum / 0.034 cum = 82 bags
similarly u can work it out for
M25 1:1:2
m15 1:2:4
m10 1:3:6
| Is This Answer Correct ? | 19 Yes | 8 No |
Answer / piyush singh
according to the IS method of design mix
1. select the grade of concrete
2. select the target strength using the equation
f(target) = Fck (selected grade) + 1.65 * sd
3. a) using the table given in IS select the maximum cement
. content
b) selecct the nominal size of the aggregate
c) water cement ration
4. then procced as code says.. and u will get actual amount
of cement , fa ,ca ,water needed for 1 M^3
| Is This Answer Correct ? | 6 Yes | 1 No |
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
| Is This Answer Correct ? | 8 Yes | 3 No |
Answer / sridhar reddy
what piyash said is write but in place of water take fine aggreate
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / ansari asif ahemad
What Piyush said is right but in place of water take Sand. I think its typing mistake.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / subbarao
by using constants of materials we have to find for 1cu.m and
then for 10cu.m
| Is This Answer Correct ? | 3 Yes | 2 No |
Answer / sanket bagade
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
| Is This Answer Correct ? | 0 Yes | 0 No |
Hai, I have applied for APPSC AEE (I&CAD) post.I need previous AEE papers of civil engineering.I hope u will kindly consider this and send.
what is the difference between onw way slab & two way slab?
Dfine superelevation.it depends upon which of the following. 1.surface condition of road 2.width of road 3.radius of curve 4.speed of vehicle
What is the unit weight of cement?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
how many litres of enamel paint required for 5000 sft of site??
How to calculate the crank length of the rod in beam? Please give me a details.
What is civgl engg?
Why alternate bars are given bent-up in slab and how to decide the length of bent up?
what is the real de-shuttering time for rcc column,slaband wall
What is approximate % of wastage considered for Marble and vitrified tiling works (flooring)?
how to preaper for interview wat they asked in interview give me idea
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)