how do we calculate the quantity cement,sand, & aggregate
for M20,M15 for 10cum.
Answer Posted / hitenpatel
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
| Is This Answer Correct ? | 8 Yes | 3 No |
Post New Answer View All Answers
why top layer of block work shoud be full size if any cut block adjustable than another layer?
all technical question
Calculation of curtain wall of box culvert
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
What in bending moment, if a moment is free end of cantilever beam?
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
Explain major difference between auto level and dumpy level?
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
what is directivity effect?
How many square meter can mason layout chb per hour
Define the various stages of the project planning process in construction.
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution
Which Types Of Bricks ?