Answer / ismail m ramsan
Sand: 0.24cm
Aggre: 0.471
Cement : 2.26 (50Kg) Bags
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / arif sherani
Cement 0.068cube
Send .0173cubi
Aggregate .03465cube
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / rajalaxmi singh
.10qntl cement,.02cum sand,.04cum aggregate.
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / snehashish basu
Cement 11 Kg, Stone chips(6 to 20mm) 0.047 Cum, Sand 0.024
Cum.
| Is This Answer Correct ? | 8 Yes | 10 No |
cement 7.2kgs
sand 0.015cum
aggregate 0.03cum
qty of concrete 0.05cum
| Is This Answer Correct ? | 0 Yes | 2 No |
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
0 Answers Anish Constructions, STUP Consultants Pvt Ltd,
Ratio of cement : sand for fixing slab and tiles in the floor and also quantity of cement and sand requires for laying slab and tiles separately (area 100 sq. ft)
Are you good at detailing and explain about the project you have worked on detailing?
5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?
what are the tests to be done for grout material, and procedure for compressive strength test procedure for grout material?
What is the minimum compressive strength of a brick according to IS codes ?
30 Answers Arup, CCCL, GMR, L&T, Rachana Sansad, Theme Engineering, WAPDA Water and Power Development Authority,
hi i am working in a civil Lab .....they asked me to find out the compressive strength of concrete cubes after 7 days of curing....the value of load on CCT machine is 205KN how to convert it to Kg/cm2 ....plzz help me...........
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.
What is absolute pressure? How absolute pressure is calculated?
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
1:5:10 isme 1 kya h 5 kya h 10 kya h
what is density of flyash?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)