Answer / ajith294
Fire and gas system usually as part of a saftey system. the
percentage of Lower Explotion limit shall be dectected by
GAS detector and gives the alarm ,normally 20% is High and
40% is High High alarm.
catalytic bead sensor, semiconductor sensor, infrared point
sensor and ultrasonic sensor are using to detect the gases.
there was no establised standared to difine zero air for
calibration. some procedure says pure nitrogen and some
uses sytetic air. But much more realisitc and practical
using ambient air for zero calibration , when area is
considered to be clean.
for span calibration using 2.5 %Methene (CH4) and balance
nitrogen mixer. 2.5 %Methene (CH4)is equal to the 50 % of
LEL.
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / mohamed yousuf
fire and gas system is nothing but to detect the toxic,
flamable and combustible gases in the plant and also for
giving the awarness of the hazardous through beacons and
loudspeakers.
| Is This Answer Correct ? | 7 Yes | 5 No |
What is upsampling and downsampling?
Explain the mechanism behind the turbine meter.
what is the difference between transmitter and smart transmitter ?
What is the difference between intrinsic instruments and ATEX instruments?
Pls can anybody tell me how much memory plc's has?in byte or in Kb
why does a transmitter o/o signal starts from 3-15psi or 4- 20mA?
A motor is taking 15 Amps at no load and 60 Amps at full load. and a valve has to open 10% at full load and 80% at no load. How to draw ladder logic.(PLC).
what is the relation between flow and pressure.for example relationship between level and pressure is p = phg like that i want ans for this question.and also how to calculate orifice sizing and flow transmitter. pls some one ans for this questions.
defination of plc
what is the field bus calble ? what are diffrences in orang colur cable and black coular calble ?
What is the procedure of DP switch calibration
in my company organisation in plan to take new PLC system for replacing old relay system , for that what I/P needsd to submit to the system house of PLC supplier?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)