concrete coverings outside steel
Answers were Sorted based on User's Feedback
Answer / ramya
15mm for slabs and lintel, 20 mm for beams, 25mm for columns and 50mm for footing
| Is This Answer Correct ? | 32 Yes | 5 No |
Answer / piyush singh
1) Slabs = minimum 15mm.
2) Beams = min 25mm.
3) Columns = min 40mm
4) piles- 40mm.
5) water tanks- 35mm.
6) foundations-40mm to 50mm.
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / ajay kumar
Concrete covering out site of steel
Slab=15 mm
Beam =25 mm
footing = 50 mm
column =40 mm
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / n. rajesh guttedar
Concrete coverings outside the steel is different is given below;
1) Slabs and walls- Not less then 15mm.
2) Beams- sides,top,bottom and ends 25mm.
3) Columns- 25mm.
4) piles- 40mm.
5) water tanks- 35mm.
6) foundations-40mm to 50mm.
70 Marine work- 40mm. to 50mm.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / r. dilli babu
Footing - 25 mm
Beam - 20 mm
Column - 40 mm
Slab - 25 mm
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / yogesh jadhav
cover to slabs between 15-20mm or 25mm
beam side AND botttom 40mm
column side cover 40mm
footing bottom cover 75mm and footing top cover 50mm
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sachin sagar
Footing = 50 mm
Columns = 40 mm
Beam = 25 mm
Slab = 20 mm
| Is This Answer Correct ? | 0 Yes | 0 No |
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
Which type of plywood & sizes using in construction projects ?
how many cement bags required for one cum of brick work the brick size is 20x10x10.
what is water cement ratio and how to calculate it after designing the concrete?
What is geographic meridian?
what's the formula for calculate pcc for matt(45mm aggregate)?
how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 digree bents plz tell me if there is any formula or tabel to find it
14 Answers Anukampa Group, AZ Engineering, L&T, Navayuga,
Define Who designed the city of Washington DC?
can any one explain structural behaviour of trapezoidal combined footing?
What is the graphical relationship between N - Value of soil and Dia. of pile when pile length is fixed, and n - Value and length of pile when its dia. is fixed.
2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;2+2=?;
What is meant by autocad?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)