concrete coverings outside steel
Answers were Sorted based on User's Feedback
Answer / subhash
slab=20mm
beam=25
column=40
footing=50
industrial building it is 75
Is This Answer Correct ? | 0 Yes | 0 No |
what is the meaning of m35 grade concrete ?
2 Answers Aparna Constructions,
why hanger rods are used in beam
for rcc which condition will u adopt now
what is minimum dimension for the kitchen & bed room
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
How to test the soil compaction test?
Define What is made from large rocks, which protects the base of cliffs?
how to calculate the required qantities of cement, Sand and aggrigate to prepare 1 Cum of concrete mix 1:2:4
What is Fly Ash & Admixture & What is the purpose of mixing Fly Ash & Admixture to Design Mix? Tell the name of commonly used Admixtures
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
How to calculate concrete,s cement, sand, metal on the bases of its ratio. For any volume of work please give me brief calculation
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?