Sales order is created 1st june for 200 tooth pastes 100
brushes free of goods (2+1 free goods). At the time of
delivery on 15th june you have shortage of brushes by 30,
offer closed on 15th june. How do you solve in this scenario??
Answers were Sorted based on User's Feedback
Answer / ashok
Hi Dear,
Since you have 70 tooth brushes available, create the SO related for the available quantity first and then create the SO related delivery for the balance qty i.e 30 no's. How ever in this case the pricing will not vary as the same has been determined in the Sales Order.
The above scenario is possible only if the customer is willing to accept partial delivery.
Regards:
Ashok
I Disk Solutions
09861991761
Is This Answer Correct ? | 12 Yes | 0 No |
Answer / noor.idea
when you face such type of questions in your interview's please keep in your mind that, the business in not done from one side or it is done as any one's like or Convinent (like we are delivering goods as we like after giving quotation).
We always a person called customer, to whom the business need to give answers for any such type of action's or decisions.
sooo. Here in this case if the material is not available the discussion well happen in between the customer and the business. then of the customer may go with any of the options like;
he can cancel the rest of the quantity, he can take the material with out free good's, he may give some more time to business to deliver the material with free goods, or he may demand for the free goods, he may claim for this false quotation.
Is This Answer Correct ? | 4 Yes | 0 No |
It depends on the company how they r practising
1 . Take the permissin from the customer and from the respective head in your company and extend the validity of the free goods for the customer and material in VBN2 for the next availability of that material.Bill the same when you procure or production of the material .
2. You can bill as per the sales order and take the permission from the customer for the rest of the brushes for later delivery . Though its not systematic . first customer should agree to this and next we have to take care how to send the rest of the brushes to customer bcz there will be no proper invoice because you have already raised it , you have to send it through manual billing with zero value for that you should be having sales tax people's permission.
3 . You can procure the rest of the brushes from the external vendor and deliver it to the customer on the same day or with permission of customer on someother day.If the material can be procured on the same day you can invoice the customer on november 15th itself.Else you have to take the permission from the customer for the delivery of brushes left on someother day .
4 . You can go for the production of the brushes. Lets say it takes 7 days to produce it . You can send the available material to customer on 15th november with proforma invoice and rest with after 7 days with someother order with manual billing and same can be accounted in the system with proper PGI and invoice.But the sale will get counted for november 22nd.Else if period is open you can do back dated PGI and invoicing .
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sudam charan swain
i think we will go for free of charge delivery after 15thfor
30 tooth brush.
Is This Answer Correct ? | 0 Yes | 2 No |
Answer / raj
Delivery him with 140 brushes with 70 free. u can do this at
delivery document you change the quantity.
Is This Answer Correct ? | 3 Yes | 7 No |
How we maintain one material at atime for two company codes?
i got a problem in printing checks online through sap. problem is that geting printing towards left i want print it in a proper position where do i configure this?
one of interviewer asked me this requirement please tell me anybody? Issue: the problem faced by us right now is,when there are more than 2 route codes available, users can select a wrong route code which is a longer route for the destination, the physical shipment can still go through a shorter route, but company will end up in paying more. Requirement: user maintained route list, the user will maintain a master from which route should be picked, users should be able to enable or disable a particular route. Thanks in advance
What sap systems have integration capabilities with sap transportation management? : transportation management
what are all the shipment activities.explain this process pls. its very urgent and what is t-code.
0 Answers Axis Global Automation,
hi,can any body let me know whether we can run mrp in third party scenerio.if so what will be its impact or result
How sales document is stuctured?
Hi Experts,What are the different tools you use for SAP SD testing and how do you use it? Explain in detail regarding its work mechanism? Please give examples from your real time data from your project. Please give examples from your real time data from your project and the tools which u are using in your project? Looking forward for your express reply...I have interview within 1-2 days. So, give reply to this query asap.. I would be very grateful to you for your timely help.Thanks in advance. Regards
on what tax is calculated on base price or net price?
what is the use of the Condition type line item called eko1 or eko2 in Sales Document. Please do not give the answer which is there in f1. Some different answer which shud be easy to uderstand. ?
Can you explain about actual GI (gods issue) date and planned GI date? Can actual GI date differ from planned GI date?
How billing document is assigned to the NLCC Delivery type?