Answer / mohsin
Using a M15 Grade Ratio is 1:2.5:5 & Quantity Is 1m3
Now Add 1.52% Dry Volume In Total Quantity
So 1*1.52=1.52
1.52/8.5=0.178
0.178/0.03472=5.15 Approximate Cement bags.
Sand=0.178*2.5
=0.44m3
Aggricate=0.178*5
=0.89m3
Cost Of Labour Cost Of Material
--------------- ------------------
Mason- 450rs Cement=220*5.15= 1133 rs
Helper-210*2= 420rs Sand=400*0.44= 198 rs
Bhisti= 180rs Aggricate=620*0.89= 551.8 rs
------------------- --------------------------------
Total rs= 1050 Total Rs = 1882.8 Rs
Now Consider the 10% of total quantity...
And 10% Contractors profits
Is This Answer Correct ? | 13 Yes | 5 No |
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
0 Answers Bhoomi Engineers Builders,
how to calculate freeboard in under ground water tank and technical details
Used Cement Mortar, Cement & Sand in 1 Square Meter or 1 Square Feet For 10-18mm Thick Plaster ? (1:6) (1:4)(1:3)
how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )
Difference between ton and metric ton
why are you joining in this (applied post) job and your aim for this job
Dear Sir What is the Contraction joint for base Slab
how many average of shuttering in one cubic meter concrete
hai,i completed my b.tech civil.Recently i wrote the appsc exam for managers water supply engg.I want answers for general studies and civil engg paper2.If any body know or written that exam send to my mail id is ruksana.sk08@gmail.com.
rate analysis of shuttering
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
why development length = 50D . why not 100D