Answer / raju
Right formula is = V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE
UNDER A1 A2 ] where , l = length , b = breadth , d = bottom
depth , h = D - d , A1 = bottom area , A2= top area (ii) is
= V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d ,
A1 = bottom area , A2= top area, Am = Mean of Top and Bottom
Area
feel free to call me
Raju
Engineer-Civil
9999213613
DLF
| Is This Answer Correct ? | 60 Yes | 3 No |
Answer / raja j
in trapezoidal footing we seperate the footing as two
parts.one is rectangle another is trapezoidal
for taking rectangular portion= (L*B*d)
L=length of footing
B=breath of footing
d=footing depth (at the end of rectangle portion height)
for taking trapezoidal
v=h/3((A1+A2)+sqrt(A1A2))
V=volume
A1= footing area (L*B)
A2= column area+ add 50mm for each side ((l+100)+(b+100))
h=height difference(D-d)
finally,
Add =rectangle+trapezoidal
= (L*B*d)+h/3((A1+A2)+sqrt(A1A2))
Raja.j
9626389621
| Is This Answer Correct ? | 9 Yes | 5 No |
Answer / jigar soni
V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d , A1
= bottom area , A2= top area, Am = Mean of Top and Bottom Area
| Is This Answer Correct ? | 5 Yes | 1 No |
Answer / s.prabhu
Please divide the footing in to 2 parts i,e 1) Bottom
rectangular portion & 2)top slope portion
Total volume (V) = v1+v2
Volume of bottom / rectangular portion is called as Volume
(v1)
Volume of top / slope portion is called as Volume (v2)
V1 = L1xB1xh1
V2= h2/3* (a1+a2)* square root of (a1+a2)
L1= length of bottom portion
B1= breadth of bottom portion
h1 = height of bottom portion
L2 = length of top portion
B2= breadth of top portion
h2 = height of top portion
a1= area of bottom bottom Portion = L1*B1
a2 = area of top rectangle portion= L2 *b2
For any clarification
Please call
S.Prabhu
9901702081
| Is This Answer Correct ? | 7 Yes | 4 No |
Answer / krishna kumar.a
Quantity = 1/6*(top area+bottom area+ 4* mean area)
Example
top length =3m, width =2m
bottom length =5m , width =4m
height =1m
Top area =3*2 = 6 sqm
Bottom area = 5*4 = 20 sqm
Mean area =(5+3)/2*(4+2)/2 = 12 sqm
Quantity = 1/6*(6 + 20 +4*12)= 12.33 cum
| Is This Answer Correct ? | 9 Yes | 7 No |
Answer / sekar.k
QUANTITY CALCULATION FOR TRAPEZOIDAL: 1/2*H(A+B)*L
EXAMPLE:FOOTING TOP WIDTH:2.00M
FOOTING BOTTOM WIDTH:4.00M
FOOTING HEIGHT :6.00M
FOOTING LENGTH :10.00M THEN,
QUANTITY OF TRPEZOIDAL FOOTING :
1/2*H(A+B)*L
1/2*6.00(2.00+4.00)*10.00
1/2*6.00(6.00)*10.00=180.00CUM
| Is This Answer Correct ? | 5 Yes | 4 No |
Answer / nadim
divide into 3 parts 1st into 2 traingles and 1 into a rectangle we all know the area formula then multiply the area with the remaining dimension
| Is This Answer Correct ? | 1 Yes | 12 No |
What is a Quick Sand?
Strength of brick?
in staad ,why we realease a moment of a member ? what is affect if we realease a moment
what is mean by bleeding of concrete
4 Answers Afcons, Habib Group,
Where can I get a Text Book on Design of Blast Resistant Buildings in PDF form.
Distinguation between Developing Length and Lapping Lengh
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
wat is the necessity of finding shear and bending moment in a structure. wat will happen if it is not consider. other than shear cracks and deflection is there any other failure happen.
what is the allowable silt % in river sand for Dam concreting.
How to check the quality of fine aggregate on site?
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
What should be the required steel in column, beam and slab
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)