HOW to calculate Rate analysis of M15 GRADE DESIGN MIX RATIO
1:2.5:5 WITH 40MM Size aggregates for 1 cumtr.
Answer Posted / mohsin
Using a M15 Grade Ratio is 1:2.5:5 & Quantity Is 1m3
Now Add 1.52% Dry Volume In Total Quantity
So 1*1.52=1.52
1.52/8.5=0.178
0.178/0.03472=5.15 Approximate Cement bags.
Sand=0.178*2.5
=0.44m3
Aggricate=0.178*5
=0.89m3
Cost Of Labour Cost Of Material
--------------- ------------------
Mason- 450rs Cement=220*5.15= 1133 rs
Helper-210*2= 420rs Sand=400*0.44= 198 rs
Bhisti= 180rs Aggricate=620*0.89= 551.8 rs
------------------- --------------------------------
Total rs= 1050 Total Rs = 1882.8 Rs
Now Consider the 10% of total quantity...
And 10% Contractors profits
| Is This Answer Correct ? | 14 Yes | 5 No |
Post New Answer View All Answers
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6
what energized you to complete your course?
how to calculate rate analysys of 1:6 plastering 10 sq m
what is the criteria for the finalisation of pavement thickness in road project?
How to calculate quantity of plum masonry in 1:3:7
what is civil enginnering & what you need of this course?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
What are the different types of civil engineering?
How to do bbs in excel format
Why should appointment store person for project ? what is the benefits for company ?
What is different between DI Pipe and CI pipe?
how many BSCs can i connect to the HUAWEI MSC
What are the basic use of runners and standards of pipelines?
how will remove spiderweb cracking in plaster ? what the reasone of make it ?