Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


In a beam tension is always at the bottom but sometimes when
we design using staad we get more number of rebars at the top
compression zone Why?



In a beam tension is always at the bottom but sometimes when we design using staad we get more num..

Answer / vikash

It is because the bottom reinforcement rebars are not sufficient to withstand the tensile stress. It generally happens in the case of doubly reinforced section. Since the bottom reinforcement are not able to nullify the tensile strength so we provide the top reinforcement in compression zone to withstand the remaining tensile stress.

Is This Answer Correct ?    7 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

number of standard bricks need 1 cubic meter

9 Answers  


Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.

0 Answers  


Whr should a joint be located in a beam if the provision of a joint is unavoidable??

2 Answers   BMTC,


m-25

3 Answers  


Define What is unit weight of normal concrete?

0 Answers  


Types of pipes?

6 Answers  


Sir your company in receiver ment of civil engineering.

1 Answers   Amrapali,


Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..

0 Answers  


How much cost is required for 1 Flyash Brick?

1 Answers  


define the engineering property of a soil. make a list of list property(properties)

2 Answers   AAI Airports Authority Of India,


mix design concrete m30 for elevated water tank

2 Answers   SITM,


how to calculate steel columns beams and slab please give me brief calculation

14 Answers   Focus, Haven Foundation, Indian Railways, Surya Builders, VICC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)