In a beam tension is always at the bottom but sometimes when
we design using staad we get more number of rebars at the top
compression zone Why?
Answer / vikash
It is because the bottom reinforcement rebars are not sufficient to withstand the tensile stress. It generally happens in the case of doubly reinforced section. Since the bottom reinforcement are not able to nullify the tensile strength so we provide the top reinforcement in compression zone to withstand the remaining tensile stress.
| Is This Answer Correct ? | 7 Yes | 0 No |
How to take labor charges for construction of 1cum of concrete?
which grade of cement mostly used in construction and why..??
U are a civil engineering student?why do u want to enter into IT industry
how much kgs should Cement,sand & aggregate to be added for 1cumt,mix is M15,M20,M25,M30
on what basis the partial factor of safety are decided? form the load combinations
what is shuttering co efficient?
9*9 1:4:8 ratio using how to calculate the material for 40mm aggregate ,cement &sand please tell me answer
how much steel provide in 1m cube r.c.c
what is the per meter weight of 50 dai steel? explain in detail?
What is the rate for RMC25 grade concreter in rs/cu mtr? What is the container capacity of RMC transporter in cu mtr?
2 Answers Akanksha, UltraTech,
What is the maximum cement content allowed in RCC?
How to calculate construction cost of residential building in mumbai
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)