Answer / ram
after approving in the purchase order then change the
quantity or price and save it know then system is show the
status is re-approval,then approve po then reseve quantity
this is one case.
Is This Answer Correct ? | 12 Yes | 4 No |
Answer / kishore kumar
1. Go to the PO Summary Form
2. Query with the required PO
3. Change the quantity or price
4. Please save and approve the PO
5. As per the approval limit it will get approved.
Is This Answer Correct ? | 4 Yes | 0 No |
You can change the quantity of a PO even after it is being
Approved. After changing the quantity, Save your work and
the status will show as 'Re-Approve'.
Is This Answer Correct ? | 2 Yes | 0 No |
what is the purpose of item master organisations? can we define more than one item master?
while shipping, under delivery tab if we didn’t mention organization/inventory will the order be back order?
Explain difference between discrete mfg and process manufacturing?
Can you update the sales order once it is booked?
in which circumstances Purchase Order Status will show as "Finally Closed"
What is inter company Transaction and set ups?
When a consultant decide or suggest to create OU and Inventory Organization ? Why the difference is ?
If owner wants to self approve then what the set-ups required?
is it possible to revise purchase requisition / internal requisition? please describe the steps
If any delivery grouping attributes in a sales order lines are different then what is the impact during pick release in shipping transaction form,What changes you observe?
How to Raise SR to Oracle?
What is the use of LC? How is it useful in export sales?