If the maximum demand is 120 KVA in a building, then what is
the Current taken according to load given ? Formula for it ?
Answers were Sorted based on User's Feedback
Answer / jose
120 kva means you have to supply 3 phase load.
3 phase load with 415 v and unity pf can take a current
according to eqn kva=1.732*Kv*I
I=120*1000/(415*1)=290 A appr
| Is This Answer Correct ? | 6 Yes | 0 No |
a Generator of 1KVA can supply upto 1.4 amps, so the maximum load could be 1.4*120
| Is This Answer Correct ? | 2 Yes | 1 No |
what are RCBO ?
How to design the NGR Resistance
what is automatic voltage regulator?we can control the vlotage by using fuzzy controller in matlab?why we go for fuzzy?
Which type of power plant is more easier to produce electrical power at economical condition?
which oil is used in transformer?
What is the difference between Isolator annd Circuit Breaker.
21 Answers ABB, Lanco, NTPC, Power Grid, RInfra,
what is an oscillator?
Any link for Electrical objective type questions ?
what kind of material to be used after ngr unit? cu or GI
In a 11KV 3phase system do you need to earth both sides of the cable?
What is knee point voltage of transformer?
what is mean by harmonics?Type of harmonics?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)