deshuttering time for RCC for DPC over the foundation.
Answers were Sorted based on User's Feedback
Answer / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
Is This Answer Correct ? | 11 Yes | 0 No |
Answer / mani d.c.e
De shuttering Beam and Slab - 1day
Slab Bottom below 3m span-14 days
Above 3m Span 21days
Beam Bottom - below 3m span - 14dayss
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / amit
for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.
Is This Answer Correct ? | 0 Yes | 2 No |
which tie is used in binding of steel double tie or single ti?
Camber of 15 mm is to be provided at free end of the cantilever what dose it mean??
What is steel requirement for one cum concrete
10mm Rebar total 12meters length how to calculate ?
How much for the BRC lapping in full yield and half yield < and which table to get it ?
Why concrete barriers have curved surface profiles?
rimmer in pile foundation
how to find soil strength,and type of soil testing?
during earth quake base shear force=a/w*g Comment?
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
which"s we should use for concrete ppc or opc?
what is calculation of cement, snd of 1:4 16mm,12mm plastring