deshuttering time for RCC for DPC over the foundation.
Answers were Sorted based on User's Feedback
Answer / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
| Is This Answer Correct ? | 11 Yes | 0 No |
Answer / mani d.c.e
De shuttering Beam and Slab - 1day
Slab Bottom below 3m span-14 days
Above 3m Span 21days
Beam Bottom - below 3m span - 14dayss
| Is This Answer Correct ? | 8 Yes | 1 No |
Answer / amit
for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.
| Is This Answer Correct ? | 0 Yes | 2 No |
how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantity of sand also
How much percentage of overlap allowed in distribution steel as per IS Code.
2 Answers Don Consult, India Cements,
What's mean fe of steel?
1 Answers Fernas Constructions,
what is the different between np2& np3 rcc hume pipe
practically where this hinge and roller condition used
Manpower required for de shuttering of conccrete slab
what is the m25 test result 7 days 14 days
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
how much cement is required for 100 sft plastering of ratio 1:4
6 Answers Confident Group, L&T, M N Creations,
How much do you want salary?
what energized you to complete your course?
What is code for designing a sheet pile?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)