deshuttering time for RCC for DPC over the foundation.
Answers were Sorted based on User's Feedback
Answer / vignesh s
For beam and slab
side deshuttering-
1 Day, slab bottom-
10Days, beam
bottom- 14Days,
cantilever beam
bottom- 16 Days
above days will be
followed after
completing the rcc
slab.
Is This Answer Correct ? | 11 Yes | 0 No |
Answer / mani d.c.e
De shuttering Beam and Slab - 1day
Slab Bottom below 3m span-14 days
Above 3m Span 21days
Beam Bottom - below 3m span - 14dayss
Is This Answer Correct ? | 8 Yes | 1 No |
Answer / amit
for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.
Is This Answer Correct ? | 0 Yes | 2 No |
What are the different theories of failure under static load?
WHAT SHOULD BE THE THICKNESS OF CEMENT M-SAND MIXER IN BETWEEN TWO SOLID CEMENT BRICKS USED FOR A HOUSE WALL?
clean earthing and dirty earthing
1 Answers CSCEC-China State Construction Engineering Corporation,
can i make bricks using M10 grade concrete ? and what would be the cost of a brick if we use m10 grade concrete sand and aggregates ??
what is mean civil
Approximate weight of a modular brick?
what is the formula for lapping length
2. What are the grades of steel used in the concrete design?
Explain different types of rcc pipes.
The compressing strength of concrete samples (cubic)
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
wht is off shore structure