deshuttering time for RCC for DPC over the foundation.
Answer Posted / amit
for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
how much tempareture are required to make liquid state of pid leed
Explain the design for rcc multi-storied building?
may i know the detailed description of cutting length
what is mean by reestimation?
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
I what know about life time of frp tank plz explain about it specifications & other details
3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
Why are steel plates inserted inside bearings in elastomeric bearing?
Questions related to civil.engg in company
what is Brest Wall?
What are the strongest shapes in building?