deshuttering time for RCC for DPC over the foundation.
Answer Posted / amit
for side shuttering=1 day
but as per is 456-2000,Bottom deshuttering of slab and beam are done when Concrete achieved 65% of its actual ulmimate strength.
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
What is portland cement
what is the anchorage length of reinforcement.
what is civil engineer greatest strength and weakness?
What is a projection line?
What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?
What is the tallest man made structure in the world?
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
what is the relation between pitch of steel and depth of slab?
Define What is passive earth pressure ?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
a butt weld is specified by
What materials were used to build the golden gate bridge?
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
What is a hatch patterns?
What are your goals?