WHAR IS DIFFERENCE BETWEEN NOMINAL MIX & DESIGN MIX IN
DETAIL
Answers were Sorted based on User's Feedback
Answer / akshay
a nominal mix is that mix in which we adopt the various ingredients such as1:2:3,1:2.5:4etc here the strength will not be the desired strength and generally here we take the ingredients per unit vol
a design mix is that mix in we find the ratio of the different ingredients as per the desired strength and the ingredients would be in per unit weight
Is This Answer Correct ? | 19 Yes | 1 No |
Answer / busireddyravi
Simply Nominal Mix is by Volume and Design Mix is By
Weight. In nominal mix We use (Cement : Fine Aggregate :
Coarse aggregate)ingredients like 1:2:3,1:2.5:4 ,here
Strenght may not be fixed it may varies, where as in Desing
the strenth may not vary much it is fixed, like after 28
days for M30 st is 30Kn/Sq.mm.
Is This Answer Correct ? | 23 Yes | 5 No |
Answer / elanthendral m.
Nominal mix concrete may be used for concrete of M 20 or
lower. The proportions of materials for nominal mix
concrete shall be in accordance with table no 9 (IS 456-
2000). above M20 grade we have to go for mix design
produces as per IS 10262-2009
Is This Answer Correct ? | 5 Yes | 0 No |
12mm diameter iron bar having 1m length how much kg weighted ?
what is the out turn of one masson in plastering, masonary work in 8 hours, with limited healper? what is the out turn of corpender in form work? wood work? in 8 hour with limited healper? what is the out turn of bar bendarin 8 hour with limited healper for slabs, beams, coloumn?
What is the graphical relationship between N - Value of soil and Dia. of pile when pile length is fixed, and n - Value and length of pile when its dia. is fixed.
Why you are leaving present job?
please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.
for pretensioning which will yield first and same for post tensioning?
1 TMC Equal to how much Cusec
if the nitrates more than 45mg/l in water lead to disease then what is it called
What is ld in beams column and slab.
In two way slab where should we stop the work at end of the day?
How much quantity of coping is done per day by one mason in Rmtr?
factor which affects design of concrete mix