• What types of scrap can be maintained in PP basic data and
how would they be considered during MRP repectively scheduling?
Answer / mohamed ibrahim
types of scrap
1- assembly scrap
increasing the assembly % in prod.order consequently increasing its components
maintain it in MRP1
2-component scrap
one component loss of QTY during production that's require increasing its QTY.you maintain this in item details in BOM and in MRP4 view
3-operation scrap
during an operation, there was a loss of QTY that require the operation scrap. you maintain it in BOM item details with check NET ID that indicates the QTY loss and also in a routine that indicates the activity loss
Is This Answer Correct ? | 0 Yes | 0 No |
What happens to planned after it has been converted into production order ?
Define mrp list
Integration between PP and MM Module.
What is the use of data in work centers?
What is the use of mrp group?
What is mrp procedure
What do we do in realization phase?
What is the difference between indian and us payroll?
SPRO path for order, confirmation or requirement class.
Explain what is the meaning of exploding a bom?
Difference between standard cost and variable cost.
How do I find which is the recurrent item in a production order? In the missing material analisys I got message MF 331, but the BOM or the production order don'thave any recurrent item Thanks