What is the percentage of steel in 1cu.m. RCC?
Answers were Sorted based on User's Feedback
Minimum reinforcement
The mild steel reinforcement in either direction in slabs
shall not be less than 0.15 percent of the total crosssectional
area. However, this value can be reduced to
0.12 percent when high strength deformed bars or
welded wire fabric are used.
Longitudinal reinforcement
The cross-sectional area of longitudinal
reinforcement, shall be not less than 0.8 percent
nor more than 6 percent of the gross crosssectional
area of the column.
NOTE - The use of 6 percent reinforcement may involve
practical diffkulties in placing and compacting of concrete;
hence lower percentage is recommended. Where bars from
the columns below have to be lapped with those in the
column under consideration, the percentage of steel shall
usually not exceed 4 percent.
| Is This Answer Correct ? | 100 Yes | 13 No |
Answer / sarath naryan nair
For slabs = 1.0 % of concrete volume.
For Beam = 2 % concrete volume.
For column = 2.5 % of concrete volume.
| Is This Answer Correct ? | 34 Yes | 2 No |
Answer / kapil gupta
minimum percentage of steel used is 1.5% for 1 cum .
for ex-if we have to build a rcc slab having voloume 10 cum and to find steel used in this rcc in kg/m is -
density of steel =7850kg/cum
and 1.5% of steel is used so simply it is the product of 7850x0.015=117.75kg for 1 cum
now for 10 cum 117.5x10=1175kg.
so for 10 cum rcc 1175 kg steel is used.
*steel more than 2% is not right way as it is very different estimate for practical calculation.
| Is This Answer Correct ? | 27 Yes | 1 No |
Answer / akash sharma (ssitm aligarh)
max 4% in column nd 2%in slab
| Is This Answer Correct ? | 31 Yes | 17 No |
Answer / danish ahmed
For slab 1%
For beam 2%
For column 2 or 2.5%
| Is This Answer Correct ? | 6 Yes | 4 No |
Soil Mechanic: You are building a gravel road. How much water do you need to mix in compact 100 m3 of road quantity borrow pit gravel?
What's is mean by survey
Compressive strength of concrete
5 Answers B L Kashyap, Era Infra Engineering,
what"s the formula to calculate the water for M15 grade concrete?
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
how can i test sand on field in lebortry?.
detailed calculation of the amount of cement used?
how you calculate the data (all parameter) after transient response method i.e.pile intigrity test on pile.
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
what do you calaculate PCC/GRADE 10
how to calculate the cement, sand, coarse aggregate required for one cubic meter of concrete?
How are freeway bridges built?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)