what is the real de-shuttering time for rcc column,slaband
wall
Answers were Sorted based on User's Feedback
Answer / shishir bhansali
rcc column 12 hours
rcc slab depending upon the span. from 5 days to 14 days
rcc wall 12 hours
| Is This Answer Correct ? | 29 Yes | 3 No |
Answer / ravi kant sharma
Minimum 16 to 18hr for column for any grade of r.c.c.
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / royalcivil
the de-shuttering time for the slab is 21 days must.
for the column it should be minimum of 1 week
| Is This Answer Correct ? | 10 Yes | 26 No |
OPC 43 OR PPC for rcc structures(raft foundation,column etc)? For M20,,which cement is better and why? for a residential structure (3 storey plus basement)
What salary do you expect? to a 10 yrs experienced civil engineer?
how to distinguish TMT n Tor steel?
which "s the best wood for commercial purpose?
Detection of a beam & a girder areββββ
For m25 1:1:2 How to get the quantities of cement,sand,agg for 1cu.mt. thnks in advnce
What is creep ,deflection and shrinkage in concrete
Explain the advantages and disadvantages of using plastic and timber fenders?
what does 1 in 30 or 1 in 40 mean when constructing camber in roads.
will fix foundation bolts at site with out template is there any procedure?
Define What is the force exerted by the Tacoma narrows bridge?
what is work of planning deptt. in any construction compny (in road project)
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)