what is the real de-shuttering time for rcc column,slaband
wall
Answers were Sorted based on User's Feedback
Answer / shishir bhansali
rcc column 12 hours
rcc slab depending upon the span. from 5 days to 14 days
rcc wall 12 hours
Is This Answer Correct ? | 29 Yes | 3 No |
Answer / ravi kant sharma
Minimum 16 to 18hr for column for any grade of r.c.c.
Is This Answer Correct ? | 8 Yes | 0 No |
Answer / royalcivil
the de-shuttering time for the slab is 21 days must.
for the column it should be minimum of 1 week
Is This Answer Correct ? | 10 Yes | 26 No |
What is the purpose of the gap in the road on this bridge?
Define What is made from large rocks, which protects the base of cliffs?
What is the primary difference between adsorption and absorption?
IS code for Rolling Margin of steel
what are the natural dynamic pressures on a structure in coastal region like chennai, vizag etc,
WHAT IS NON DESTRUCTIVE TEST?PLEASE GIVE ME THE PROCEDURE?
how do we find the nos of bricks in 1 m3 brick masonary
in which measurment pitot tube is used
What is the cement and sand consuption of 1:4 block work
What is the quantit;(pratical method) of cement, sand, and gravel to be used in M25 grade of concrete for 1000 x 1000 x 1000 mm of sand (for cement please mention in kilos, and for sand and gravel please mention in cuft
which tests for concrete pouring period at the site?
what is the minimum cement content for rcc as per is code