Please tell me the difference between nominal and clear
cover. Thanks.
Answer Posted / mustafa mohd layeak
In beam of b*D dimension. considering bottom section of beam
effective cover is the distance between centre of main
bottom longitudinal rebar to the concrete extreme fibre
(bottom edge of beam).
clear cover is distance between concrete extreme fibre and
bottom edge of a stirrup
Similarly at the top section of beam
| Is This Answer Correct ? | 45 Yes | 8 No |
Post New Answer View All Answers
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
Forces in a Shear Wall are in plane or out of plane ?
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
How can explode a block?
IS STEEL BARS IS AS PER ISI TRANSVERSE RIBS SHOULD BE UNIFORM IN DISTANCE, PLEASE EXPLAIN WHY,
What is the difference between 53 grade and 43 grade cement
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
whaat is blister in box girder bridge and what is its function..
What is need for setting limits?
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
how to calculate rate analysys of 1:6 plastering 10 sq m