how to estimate the earthwork,earth-filling for an isolated
foundation
Answers were Sorted based on User's Feedback
Answer / d. baby
size of footing x depth of footing = earthwork qty
a x b x d = qty
total earthwork - isolated footing qty = earth filling
| Is This Answer Correct ? | 15 Yes | 3 No |
Excavation > is l x b x h
but filling is total excavation - pcc-rcc of footing up to NGL
| Is This Answer Correct ? | 7 Yes | 1 No |
Answer / ramcharan
Earth quantity = aria isolated footing + working margin
Earth filling quantity = earth quantity _ isolated footing
| Is This Answer Correct ? | 4 Yes | 1 No |
Sir your company in receiver ment of civil engineering.
how to do reconciliation of steel
per 1 cumt concrete how much manhours is required including shuttring,steel etc.,for slab & foundations
what is the allowable silt % in river sand for Dam concreting.
How to rectify thermal cracks (2mm wide, 9mm deep aprx. ) developed in tremix finished concrete floor?
Please tell me present is code no for steel structure work. Thanks.
How you can turn off the display for dimension in CAD?
What will be compressive strength of concrete casted in PPC in the 7 days period with M20 grade.
what is the quantity out-put by Hitachi-200 breaker for breaking or how to calculate
what is the used civil engg?
Explain what is the difference between built area and super built up area?
how we can calculate a bentup hook in difreeent angles.for exp.at 90 degree,45degree,60 degree..
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)