How can we cross check the excavation and backfilling
quantities.
Answers were Sorted based on User's Feedback
Answer / praman srivastava
In case of foundation like Load Bearing , Isolated footing
or raft , Total excavation calculated as per plan & require
depth form NGL & deduct the total qty of pcc cc or B/w up
to NGL,then total balance qty is known as backfill.Approx
60% qty.of excavation is required for back fill.
Is This Answer Correct ? | 8 Yes | 0 No |
Answer / ajay
In case of building it will be 60%
In case of normal excavation it will be 90% without compaction
In case of compaction it will be 100%
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sjtbehera
cross check of these items are not possible where
everything done. you can take theoritical value or actual
cutting
Is This Answer Correct ? | 1 Yes | 3 No |
how much one carpenter can doing shuttering of slab in one day
what is meant by expansion joints in concrete structures?
What are the uses of alloys in daily life and how are alloys made?
What is the difference between absorption & adsorption and sorption?
HOW we can calculate the quantity of sand and cement for 1:4 plastering with a thickness of 12 mm..total area need to be plaster is 985 sqm
why red bricks & cinders used in toilet sunken filling. if coarse aggreate used wat the probelem
cement constant for brick works
what is general scouring?
How to design staircase.plz tell me formula for the design the staircase.
please describe clear cover in column from stirups to face
How to calculate quanty of steel in four leg stirrups?
Which is the direction for positive angle?