How can we cross check the excavation and backfilling
quantities.
Answer Posted / praman srivastava
In case of foundation like Load Bearing , Isolated footing
or raft , Total excavation calculated as per plan & require
depth form NGL & deduct the total qty of pcc cc or B/w up
to NGL,then total balance qty is known as backfill.Approx
60% qty.of excavation is required for back fill.
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
What in bending moment, if a moment is free end of cantilever beam?
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
What are the responsibilities of a construction manager?
Define graphics window?
What is the general specifications of a bituminous pavement road?
What is alternate bid?
Design a rectangular channel.
What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
How to construct a water sump in a rocky soil?
How to calculate woden area in sft and Cft
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
What does civil status mean?
what is called the inverd level of mabhole chamber?