how many average of shuttering in one cubic meter concrete
Answer Posted / ilias mahammad
Shuttering Qty can be taken as approx.5-6 times the volume
of concreting.
i.e. for 1 cum of concreting approx. 5.00sqm-6.00sqm
shuttering is required.
Is This Answer Correct ? | 19 Yes | 3 No |
Post New Answer View All Answers
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
how can calculate cutting length of diamond ring
What is unit weight of normal concrete?
How many days should curing of plastering, brick work and concrete
What are the different types of civil engineering?
how many digree of freedom in four bar chain
For the construction project what capital cost has to be taken in consideration?
what is the construction cost for per cft of multistorryed building in kolkata?
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.
Explain what are the skills required to become an architect?
if the nitrates more than 45mg/l in water lead to disease then what is it called
minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork