how many average of shuttering in one cubic meter concrete

Answer Posted / ilias mahammad

Shuttering Qty can be taken as approx.5-6 times the volume
of concreting.
i.e. for 1 cum of concreting approx. 5.00sqm-6.00sqm
shuttering is required.

Is This Answer Correct ?    19 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.

1725


factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard

1671


how can calculate cutting length of diamond ring

1374


What is unit weight of normal concrete?

682


How many days should curing of plastering, brick work and concrete

1213






What are the different types of civil engineering?

652


how many digree of freedom in four bar chain

1920


For the construction project what capital cost has to be taken in consideration?

678


what is the construction cost for per cft of multistorryed building in kolkata?

1789


in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.

1728


hai, kindly send anyone for output workers format details for construction project in foundation to finishing.

1074


Explain what are the skills required to become an architect?

705


if the nitrates more than 45mg/l in water lead to disease then what is it called

2346


minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?

4875


How much sand and cement requirement for 1 SQM 125mm thickness Brickwork

557