Answer / mehul g. c.
single phasing is the fault in that one of three phase will
break or not proper then machine or equipments will get
unbalance.
my mean to say is suppose r,y&b is three phase & y is not
showing voltage for some reason than it is single phasing.
if it is happens then machine will not work proper it will
get heated because of phase unbalancing or burnt.
| Is This Answer Correct ? | 39 Yes | 3 No |
Answer / abhishek (balco)
if 1 phase is out then machine works with two phase with
heavy losses. it takes very high current..
| Is This Answer Correct ? | 17 Yes | 2 No |
Answer / mehul g. c.
dear abhishek,
if it will take high current at single phasing then
equipment damage because of that only single phase preventer
devloped.
| Is This Answer Correct ? | 9 Yes | 4 No |
Answer / falguni
if any one of 3 phases i.e. in r, y & b if r is not working
properly is called single phasing.
| Is This Answer Correct ? | 8 Yes | 3 No |
In 1 of the three phases,any of one phase was get affect
due to unbalance of cable or busbar champer with breaker
isolator connection get loose,it will reflect by no current
and less voltage on that particular phase and utilisation
of equipement also shown problem on that phases. i was
faced this problem in previous plant as from lighting
distribution panels problem..
by S.venkatesh
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / devganiya rahul
In the 3 phase electrical appliances/equipment if one phase is cutoff due to some reson then it is called single phasing.
| Is This Answer Correct ? | 0 Yes | 0 No |
How to calculate the load loss and no load losses of the power Transformer? i am having the following details : full load ct : in AMP HV :1676 ; LV:31.5 1800 KVA ;33KV/620 V for wind mill applications
why do we earth the tandelta point of a power transformer bushing?
if an insulated power and control cables of a running gas diesel gensets laid direct in an open trench i.e, trench bed is not rcc of a power house in which rain water, spillage water alwas exists and all power control cables remains submerged even when gas gensets of 480 kw each runningin on load. These power &control cables runs from power house to switchgear room through these trenches in which water remains most of the time. pl explain its merit & de-merit
Define maximum demand?
please explain how to do 'pole drop test' on generator?
What is the purpose of RECTIFIER ASSEMBLY in AC power generators?
Arrangement of earthing materials.like what we put first charcol,then salt.then plate. Plz answer me about that.
71ohm,111ohm,95ohm,179ohm in calculate the total ohm in series circuit
What is the general power factor & min. power rating of TV,LCD type TV, CRt type TV, Scanner, printer?
In ac which gas will be use?
what is skin effect? why is it absentin dc system
what is The difference between national electrical code and I.S.Code (electrical) and what is the value of NEC in electrical engineering field
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)