Answer / sidharth
well its in year 2000. The basic change is, for all RCC
work the minimum grade of concrete becomes M-20 instead of
M-15
| Is This Answer Correct ? | 35 Yes | 3 No |
Answer / chetan biraris
NEW REVISION is IS 456-2000,
REVISIONS ARE
1.DETAILED CLAUSE COVERING DIFFRENT ASPECTS OF DESIGN OF
DURABLE STRUCTURES HAS BEEN INCORPORATED
2.IN GRADES OF CONCRETE..GRADE MORE THAN M40 HAS BEEN ADDED
| Is This Answer Correct ? | 22 Yes | 2 No |
Answer / j.venkatesh perumal
IS 456 revised in 2000
RCC concrete minimum grade M15 to M20
| Is This Answer Correct ? | 11 Yes | 2 No |
Answer / rehana
in 2000 if any who don't know plz don't bother any one alse.
| Is This Answer Correct ? | 10 Yes | 3 No |
Answer / sathyajeth
it has been revised in 2000 and it has changed m15 grade to
m20
| Is This Answer Correct ? | 10 Yes | 3 No |
Answer / nikul prajapati (baroda)
ITS IN THE YEAR OF 2000 IT IS REVISED LASTLY.........
| Is This Answer Correct ? | 6 Yes | 1 No |
Answer / mainak majumder
IS 456:2000(reaffirmed 2005) is fourth revision.other than
M@0 is minimum grade & grades higher than M40 many things
are incorporated.all taht things is written in 1st two pages
of IS 456..plz read those things.
| Is This Answer Correct ? | 4 Yes | 1 No |
how to calculate the weight of concrete
what is the mean of opc cement and conceret grade 53 n?please explane with detail>
How we decide the the load combinations for design of RCC structures?
what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon
how to calculate column load bearing? how many weight capacity in 1m3 concrete? pls answere me sir.
which is the cheapest type of flooring (say for using for 6 months in a factory building & dismantling it)?
how many liters of water required for 1cu.m concrete?
what is the status of Brick & cube testing
describe about Hollow bricks? where the hollow brick "ll use& what"s the purpose?
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
what is the weight of 12 mm 40 mm aggregate?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)