curing duration
Answers were Sorted based on User's Feedback
Concrete will give strenght after completion of reactions
in cement .The concete will give 67 % strenght in 7 days
75% Strenght in 14 days 98% strenght in 28days and 100 % in
one year.so we have to cure concrete for a minimum period
of 28 days for complete the reactions in cement and get
strengh
| Is This Answer Correct ? | 75 Yes | 16 No |
According to hydration process and strength gaining process
of cement 28 days curing is required but according IS code
of opc cement 7 days curing is required and in ppc 14 days
of curing is required. But above of all continuous curing
is very important for any construction instead of how many
days we cure it.
| Is This Answer Correct ? | 24 Yes | 5 No |
Answer / girish kumar v k
Gentlemen there is nothing Technical behind the concept of Curing.Logic is what behind this.
As per IS 456, the grade of the concrete itself indicates the strength of the Concrete after 28 days,..right?
Then curing has to be done for 28 days in order to test the Compressive strength of the concrete.
What I would say is.. without curing for 28 days how can you carry out the test and say that the member which contains the concrete equals the strength that off the cube strength. This concept is purelly Illogical.
To ensure whether the member has attained strength, cubes have to be kept on/adjacent to that particular member (Slab, beam,girder,column) and then curing to be carried out. Now curing will happen equally and simultaneoulsy to both.
Afterwhich testing of cubes will actually give the strength of the member
Else If curing is done for 7/14 days then test the cubes only for that particular period, which also signified same strength for the member.
But curing for 7/14 days only would lead following
1. Low compressive strength then required as per Design mix
2. Lesser durability of concrete
3. Increased permeability
4. Concrete becomes brittle & breaks due to improper hydration.
| Is This Answer Correct ? | 18 Yes | 3 No |
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
Sir what reason the deshuttring of column 1 day after casting and slab deshuttring time 14 days after casting
Is there any codal provision stating the actual diameter for chair bars?
what is the max. dia of steel can be used in open footings?
what is the difference in density of fresh concrete and hardened concrete?
1 Answers GPSC Gujarat Public Service Commission,
Difference between wbm and gsb in road construction
4 Answers CPWD, GSB, Ircon, JMC Projects, L&T, RD,
what opc & ppc cement $ composition?
why does the most of civil engg is not intersted to going for teaching field?
for plaster what is the suitable sand.
how new RCC roof joined with existing RCc roof
whate the size of bricks are avalable at site
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)