curing duration

Answers were Sorted based on User's Feedback



curing duration..

Answer / suresh

Concrete will give strenght after completion of reactions
in cement .The concete will give 67 % strenght in 7 days
75% Strenght in 14 days 98% strenght in 28days and 100 % in
one year.so we have to cure concrete for a minimum period
of 28 days for complete the reactions in cement and get
strengh

Is This Answer Correct ?    74 Yes 16 No

curing duration..

Answer / deepak kumar

According to hydration process and strength gaining process
of cement 28 days curing is required but according IS code
of opc cement 7 days curing is required and in ppc 14 days
of curing is required. But above of all continuous curing
is very important for any construction instead of how many
days we cure it.

Is This Answer Correct ?    24 Yes 5 No

curing duration..

Answer / girish kumar v k

Gentlemen there is nothing Technical behind the concept of Curing.Logic is what behind this.
As per IS 456, the grade of the concrete itself indicates the strength of the Concrete after 28 days,..right?
Then curing has to be done for 28 days in order to test the Compressive strength of the concrete.
What I would say is.. without curing for 28 days how can you carry out the test and say that the member which contains the concrete equals the strength that off the cube strength. This concept is purelly Illogical.
To ensure whether the member has attained strength, cubes have to be kept on/adjacent to that particular member (Slab, beam,girder,column) and then curing to be carried out. Now curing will happen equally and simultaneoulsy to both.
Afterwhich testing of cubes will actually give the strength of the member
Else If curing is done for 7/14 days then test the cubes only for that particular period, which also signified same strength for the member.
But curing for 7/14 days only would lead following
1. Low compressive strength then required as per Design mix
2. Lesser durability of concrete
3. Increased permeability
4. Concrete becomes brittle & breaks due to improper hydration.

Is This Answer Correct ?    18 Yes 3 No

curing duration..

Answer / roopa

28 days only

Is This Answer Correct ?    13 Yes 8 No

curing duration..

Answer / n.s.faiyas

7 to 14 days

Is This Answer Correct ?    15 Yes 18 No

Post New Answer

More Civil Engineering Interview Questions

why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 days..

7 Answers  


What are the types of slump?

0 Answers  


How to find CN by using arcgis 9.3?

0 Answers  


five requirements of infill panels for walls?

0 Answers  


how calculate cutting length of stell in slab and column? give brif discussion with formula?

3 Answers   ATS, Gammon, Pegasus,






does the compressive strength of brick be more then 3.5 n/mm2 or 5 n/mm2?

3 Answers   L&T, Modi Builders,


WHAT DO YOU MEAN BY MIX DESIGN OF CONCRETE?NAME THE VARIOUS METHODS OF CONCRETE MIX DESIGN.EXPLAIN I.S.METHOD OF MIX DESIGN

0 Answers  


What is the allowable silt content for concrete works?

2 Answers   Sepco,


how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantity of sand also

3 Answers  


What is progress payment?

0 Answers  


At which place Construction joint should provide in slab and Beam at the time of casting.

3 Answers  


# 1. size of the Bricks # 2. Minimum Crushing Strength of Bricks

5 Answers   Brigade,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)