Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What is the difference between Design and nominal mix?

Answers were Sorted based on User's Feedback



What is the difference between Design and nominal mix?..

Answer / anandsamy

Asper IS456 nominal mix is prescriptive type...like 1:2:4...
But design mix is performance based..u want to design the grade..ratio...etc...

Is This Answer Correct ?    3 Yes 0 No

What is the difference between Design and nominal mix?..

Answer / ishesh

Design mix by weight with use admixture &Nominal mix by volume with fix ratio of cement, sand,aggregate.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what post do you prefer to work in this company and why do you think you can serve better in such position?

0 Answers  


What is the standard unit of bricks???

2 Answers   L&T,


How much steel and concrit required in 1000 square feet slab?

2 Answers  


I dont know english very well to speak,in interview if they ask to introduce yourself means how to answer in english?

2 Answers   GMR,


what is mean by super structure?

25 Answers  


How to calculate the amount of cement & sand required for plastering work with ratio 1:4 please give me an answer with detailed step.

6 Answers   DSR Management, Simplex,


what are the major benefit in auto level?

1 Answers  


Whats the meanig of ,'K' VALUE in the case of soil.....

0 Answers  


how do you measure the 1:2:4 and 1:1:2 proportion rcc concrete for one cubic metre? what is the cement qty. sand qty. jelly qty.

1 Answers   VR Residency,


In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment

8 Answers   Power Grid,


what affect on the structure and related beam of slab when provide one way slab insteade of two way slab

2 Answers  


what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)