Where we will give the penalty for delay in supply to the
Supplier?
Answers were Sorted based on User's Feedback
Answer / vamshi
If it is a permanent supplier we generally mention it in
the MSA(Master Service Agreement) or sometimes we usually
mention in the SLA(service level agreement) also
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / yogesh agrawal
There is no separate provision for penalty, usually it is
entertained by writing footnotes in purchase order and is
called LD (Liquidated Damages) clause. It is mentioned
like" LD is applicable @0.5% per week if the goods are
delivered after < date/ weeks> LD will be determined by the
overdue days/weeks". There is one more way out when
calculating supplier performance report.
| Is This Answer Correct ? | 4 Yes | 3 No |
How can u put inventory on hand value is negative?
If owner wants to self approve then what the set-ups required?
what are the tables used for the item catalog conversion and similarly mandatory columns along with validations?
Name of the reports in oracle inventory related to transaction????
Where we will give the penalty for delay in supply to the Supplier?
What is the difference between expense item and inventory item ????
How many KFF are there in Order management? What is the use of Sales Order Flex-Field?
can u tell me the upgradation issues in oracle apps
How does Oracle apps come to know that entered order is back to back or Standard sales order if in both the cases item is ATO type?
Can you update the sales order once it is booked?
how to find customer is new or old in order management
How do you create purchase order without requisition? Please provide the answer if you know