Where we will give the penalty for delay in supply to the
Supplier?
Answers were Sorted based on User's Feedback
Answer / vamshi
If it is a permanent supplier we generally mention it in
the MSA(Master Service Agreement) or sometimes we usually
mention in the SLA(service level agreement) also
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / yogesh agrawal
There is no separate provision for penalty, usually it is
entertained by writing footnotes in purchase order and is
called LD (Liquidated Damages) clause. It is mentioned
like" LD is applicable @0.5% per week if the goods are
delivered after < date/ weeks> LD will be determined by the
overdue days/weeks". There is one more way out when
calculating supplier performance report.
Is This Answer Correct ? | 4 Yes | 3 No |
1.Is it mandetory to recieve an expenses item,if we do not recieve what would be the PO status.? 2.Can we Open a closed PO.?If yes,How...?
How is the charge account defaulted in Purchasing document(Requisition, PO)?
How do you define an expense type or asset type item??
May i know some of the real time issues we face in oracle purchasing, inventory and Order Management.
What are the different types of RG Registers?
What are the different types of excise exemptions?
The item attribute ‘Reservable’ is No - what is the impact?
What is the use of INV-Receipts and PO-Reciepts,Just give me the Differences&When,At what Instances to use Them...?
How many item master organisations can be created in Multi org structure ??????
in the support project, what are issues u faced?
What are the FAQ's asked Functional consultants in SCM ? If any one knows please send.
Even though Item attributes are correctly set and item is assigned to OE Item validation organization still the item in not available while creating SO. What is the cause?