Where we will give the penalty for delay in supply to the
Supplier?
Answers were Sorted based on User's Feedback
Answer / vamshi
If it is a permanent supplier we generally mention it in
the MSA(Master Service Agreement) or sometimes we usually
mention in the SLA(service level agreement) also
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / yogesh agrawal
There is no separate provision for penalty, usually it is
entertained by writing footnotes in purchase order and is
called LD (Liquidated Damages) clause. It is mentioned
like" LD is applicable @0.5% per week if the goods are
delivered after < date/ weeks> LD will be determined by the
overdue days/weeks". There is one more way out when
calculating supplier performance report.
| Is This Answer Correct ? | 4 Yes | 3 No |
IF user wants to ship the lines in single delivery when there are different delivery id created for a Sales order, then what process has to be followed
What if when physical count differs from system count?
Auto pick confirm whether required or not where is that set-up done? Other than OM System parameters where else?
The item attribute ‘Reservable’ is No - what is the impact?
Diff b/w Discrete mfg and Process manfactureing? If anyone have the detailed steps on this topic, please forward to me yakumar47@gmail.com
Hi, I just want to know the best institute to learn (oracle apps scm functional) in hyderabad ?
Can i make restrictions for sales order? Like, book the sales order only for 100 or above quantities?
New Item is manufactured and we can do internal transaction but this item would be ready for sale from August 1st. where do we update start date for this item to available in Sales order?
What are all the difference between version 11i and R12 ??? Will anybody explain to me ???????
How to define vacation rules in Oracle Purchasing upon User Request?
while shipping, under delivery tab if we didn’t mention organization/inventory will the order be back order?
What is meant by Position Hierarchy and Supervisor Hierarchy ????