How do you determine realistic schedules for the project?
Answer / hyejung kwon
According to Verzuh, a realistic schedule:
-Includes a detailed knowledge of the work to be done
-Has task sequences in the correct order
-Accounts for external constraints beyond the control of
the team
-Can be accomplished on time, given the availability of
skilled people and enough equipment
There are steps to follow to create realistic project plan.
Step one: Create a work breakdown structure
Step two: Identify task relationships (Network
Diagrams/PERT Charts)
Step three: Estimate work packages
Step four: Calculate an initial schedule
Calculating the schedule is a three-step process; forward
pass, backward pass, and calculate float. Forward pass
helps you determine the early start (ES) and early finish
(EF) for each task. Backward pass determines the late start
and late finish dates. Calculate float means flexibility in
the schedule and calculated buy subtracting early start
from late start. Critical path has no float, so it should
begin and finish on time.
Step five: Assign and level resources
Resources mean the people, equipment, and the materials.
And the leveling follows a four-step process:
1. Forecast the resource requirements throughout the
project for the initial schedule.
2. Identify the resource peaks.
3. At each peak, delay noncritical tasks within their float.
4. To eliminate the remaining peaks, reevaluate the work
package estimates.
This detail and realistic schedule may not solve all the
problems but wil provide a tool set for solving many of
them.
| Is This Answer Correct ? | 79 Yes | 11 No |
Describe your ideal job and/or boss.
Cisco vs HP vs IBM vs Dell
what is your self n what is your hobise n why?
DataStage 7.5 & DataStage 8.5 :Which Oracle Database version is supported as target datasource?
what is difference between a primary market and secondary market in us economy as per e-commerce point of view ?
Do you personally involved with Major incident process ? If yes, how do you manage it in your present organization ? explain with real scenario !
what do you mean by "Closures with help of Top Management and Colleagues"
What change management processes have you used to ensure that change is introduced properly?
i was looking for a general example for time management and how everything is linked together so i can have a complete picture. when i say link i mean with OM and PA and work schedule,planned working time, other relevant infotypes, personnel area and subarea and their groupings, etc...
Does S5700-24TP-SI-AC support dual power?
What is security policy? To protect an organization’s information what security policy need to follow according to you.
What type of questions will be asked in Bank of India Computer Officers (IT) exam? Will someone provide me the sample paper of Bank of India Computer Officer (IT) exam?
Business Administration (517)
Marketing Sales (1279)
Banking Finance (3208)
Human Resources (747)
Personnel Management (68)
Hotel Management (29)
Industrial Management (113)
Infrastructure Management (14)
IT Management (97)
Supply Chain Management (16)
Operations Management (39)
Funding (79)
Insurance (494)
Waste Management (1)
Labor Management (48)
Non Technical (73)
Business Management AllOther (546)