How do you determine realistic schedules for the project?

Answer Posted / hyejung kwon

According to Verzuh, a realistic schedule:
-Includes a detailed knowledge of the work to be done
-Has task sequences in the correct order
-Accounts for external constraints beyond the control of
the team
-Can be accomplished on time, given the availability of
skilled people and enough equipment

There are steps to follow to create realistic project plan.
Step one: Create a work breakdown structure
Step two: Identify task relationships (Network
Diagrams/PERT Charts)
Step three: Estimate work packages
Step four: Calculate an initial schedule
Calculating the schedule is a three-step process; forward
pass, backward pass, and calculate float. Forward pass
helps you determine the early start (ES) and early finish
(EF) for each task. Backward pass determines the late start
and late finish dates. Calculate float means flexibility in
the schedule and calculated buy subtracting early start
from late start. Critical path has no float, so it should
begin and finish on time.
Step five: Assign and level resources
Resources mean the people, equipment, and the materials.
And the leveling follows a four-step process:
1. Forecast the resource requirements throughout the
project for the initial schedule.
2. Identify the resource peaks.
3. At each peak, delay noncritical tasks within their float.
4. To eliminate the remaining peaks, reevaluate the work
package estimates.
This detail and realistic schedule may not solve all the
problems but wil provide a tool set for solving many of
them.

Is This Answer Correct ?    79 Yes 11 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

could you provide me the information regarding UNIVESAL WORK LIST(UWL)?this question is regarding SAP EP.

2391


How we do trimming in Solaris and how to prevent the /var from become disk full.

1495


What type of questions will be asked in Bank of India Computer Officers (IT) exam? Will someone provide me the sample paper of Bank of India Computer Officer (IT) exam?

2021


DataStage 7.5 & DataStage 8.5 :Which Oracle Database version is supported as target datasource?

2934


what is variable?

2026






7. (a) How do you implement internal controls in IT systems? (b) How to design internal controls over financial reporting, when financial reporting is performed totally from the software application? Explain briefly the major points. (c) What are the additional controls needed, when the software interfaces are webbased? Explain the materiality of the payroll processing functions to be performed by webinterfaces from the control perspective.

1899


Describe your ideal job and/or boss.

3951


a. Explain the three (3)  Facets of Supply Chain b. Explain the work of logistics c. Explain the three (3) description of customers d. Explain the importance of information technology in logistics

1806


what is capital

2135


what is the difference between BI and BW security?

2004


Why general ledger accounts require "post automatically" setting in SAP??

1501


What is computer-based information system (CBIS) mean?

2209


what do u mean by altkey?

1955


Is any one has SAP GTS( Global Trade Services)Reading and Exercise material. If so, please e-mail me.

3295


Hi, I worked TCS (BA) third party for only 18 days. After that i didnt go to office due to some problem. i send resign letter through mail.Just i want to know whether its affect my career.? also my consultant is drop the mail TCS is ben for me so its true ...i need to pull back agin try. so its posssible Pls guide me

1093