What is "Readjustig goal and Milestone" in project
managment and project planing

Answers were Sorted based on User's Feedback



What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / tushar waghode

Re-adjusting goals can be viewed as a part of change
management where impact of changes result in change of
scope of the deliverables or project.
Milestone is used as a checkpoint at logical points in a
schedule to ascertain completeness of work at that point.
In Microsoft project a milestone is a zero duration, zero
resource intentive activity.

Is This Answer Correct ?    25 Yes 2 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / rashmi ranjan sinha

Milestone: Date by which major activities are performed.
Readjusting: If the milestone seems not to be achieved as
targeted or incur a risk, it should be readjusted setting
goals with different approach.

Is This Answer Correct ?    17 Yes 5 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / manzoor

The recognition of an important event within the project,
usually the achievement of a key project deliverable

Is This Answer Correct ?    9 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / san

milestone is a point were we can check our process
achivements steps and if are not in proper way throu we
must here come readjusting goal. every team always go to
this process planing->devlopment->testing in time sedule.
if it not happen goto Readjustig goal same work in diffrent
way

Is This Answer Correct ?    12 Yes 8 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / a dilipkumar

Ideally both Goals and Milestones(completion/sign-off of a
major activity or deliverable) are fixed at the beginning
of the Project Planning Phase based on the Project Charter.
However, during certain cases, during the course of the
project, the goals and/or milestones becomes irrelevant to
the changed business context. Hence, instead of pursuing
the earlier establised goal, with the apporval of the
Project Sponsor (who had approved the Project charter), the
goals and subsequently the milestones to achieve the
revised goals can be planned and changed to reflect the
revised business requirement.

Is This Answer Correct ?    4 Yes 2 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / saravanan

In addition to above mentioned points, During Project
development process, whenever there is a requirement
change / requirement correction happens. PM will need to re-
adjust the goal and milestone.

Is This Answer Correct ?    6 Yes 6 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / indranil bhattacharya

"Readjustig goal and Milestone" is a common technique used
in large projects. Here depending upon the requirement we
need to change the Scope of the project resulting the
deliverable vs. time table. Here always we need to keep in
mind about the BAC (budget at completion) of the project.

Is This Answer Correct ?    3 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / cristina giese

Readjust goals and milestones can be shares resulting from process of change management, where a scope change was requested and approved and will be implemented.
This action affects the entire project planning because it is necessary to revise the scope, cost estimating, the schedule and project risks. Just as the baseline.

Is This Answer Correct ?    0 Yes 0 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / surender yadav

The Partial blocks of achievement is a milestone.
Particulary for projects more than of 6 months period If
percieved due to constraint -Technology Change , fresh
demand from customer(changing the SOW),products becoming
obsolete there can be mutual negotitation to change the
milestone dates (some times penalty may be leivied) and the
goal.

Is This Answer Correct ?    2 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / amarnath

It is a process which must be carried out during the
project Management or to be planned during the project
planning stage to list the actions to be taken in case of
any requirement changes arises. This term is used while
communicating with the stakeholders. For example, “If there
are any changes in the system requirements we need to
Readjust the goal and milestones” and if the stakeholders
ask, we should be able to list the planed steps for the
process, which depends on the project in hand.

Is This Answer Correct ?    1 Yes 2 No

Post New Answer

More Project Management Interview Questions

You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following? A. Using the previous project's alternatives identification as a template B. Reusing the previous project's benefit/cost analysis as justification for this project C. Using the previous project's WBS as a template D. Reusing the previous project's product description when writing the scope statement

0 Answers  


Which of the following is true regarding the scope statement? A. It describes how to make changes to project scope. B. It describes project deliverables and serves as a baseline for future project decisions. C. It assesses the stability of the project scope and is a baseline for future project decisions. D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.

0 Answers  


You work for a large manufacturing plant. You're working on a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true? A. The new machine, the concentrated formula, and the smaller package are each project constraints. B. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document. C. The new machine, the concentrated formula, and the smaller package are each project assumptions. D. The new machine, the concentrated formula, and the smaller package are each considered deliverables.

0 Answers  


How will you measure software quality?

0 Answers  


Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT

0 Answers  






Which of the following processes serve as inputs to each other? A. Executing and Controlling B. Planning and Executing C. Planning and Controlling D. Executing and Initiation

0 Answers  


You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150

0 Answers  


All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance

0 Answers  


You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram

0 Answers  


The theory that 85 percent of the cost of quality is a management problem is attributed to: A. Doming B. Kaizen C. Juran D. Crosby

0 Answers  


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4

0 Answers  


Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true? A. This project came about due to customer request, and the primary constraint is time B. This project came about due to market demand, and the primary constraint is time. C. This project came about due to market demand, and the primary constraint is quality. D. This project came about due to customer request, and the primary constraint is quality.

0 Answers  


Categories