What is "Readjustig goal and Milestone" in project
managment and project planing

Answers were Sorted based on User's Feedback



What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / tushar waghode

Re-adjusting goals can be viewed as a part of change
management where impact of changes result in change of
scope of the deliverables or project.
Milestone is used as a checkpoint at logical points in a
schedule to ascertain completeness of work at that point.
In Microsoft project a milestone is a zero duration, zero
resource intentive activity.

Is This Answer Correct ?    25 Yes 2 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / rashmi ranjan sinha

Milestone: Date by which major activities are performed.
Readjusting: If the milestone seems not to be achieved as
targeted or incur a risk, it should be readjusted setting
goals with different approach.

Is This Answer Correct ?    17 Yes 5 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / manzoor

The recognition of an important event within the project,
usually the achievement of a key project deliverable

Is This Answer Correct ?    9 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / san

milestone is a point were we can check our process
achivements steps and if are not in proper way throu we
must here come readjusting goal. every team always go to
this process planing->devlopment->testing in time sedule.
if it not happen goto Readjustig goal same work in diffrent
way

Is This Answer Correct ?    12 Yes 8 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / a dilipkumar

Ideally both Goals and Milestones(completion/sign-off of a
major activity or deliverable) are fixed at the beginning
of the Project Planning Phase based on the Project Charter.
However, during certain cases, during the course of the
project, the goals and/or milestones becomes irrelevant to
the changed business context. Hence, instead of pursuing
the earlier establised goal, with the apporval of the
Project Sponsor (who had approved the Project charter), the
goals and subsequently the milestones to achieve the
revised goals can be planned and changed to reflect the
revised business requirement.

Is This Answer Correct ?    4 Yes 2 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / saravanan

In addition to above mentioned points, During Project
development process, whenever there is a requirement
change / requirement correction happens. PM will need to re-
adjust the goal and milestone.

Is This Answer Correct ?    6 Yes 6 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / indranil bhattacharya

"Readjustig goal and Milestone" is a common technique used
in large projects. Here depending upon the requirement we
need to change the Scope of the project resulting the
deliverable vs. time table. Here always we need to keep in
mind about the BAC (budget at completion) of the project.

Is This Answer Correct ?    3 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / cristina giese

Readjust goals and milestones can be shares resulting from process of change management, where a scope change was requested and approved and will be implemented.
This action affects the entire project planning because it is necessary to revise the scope, cost estimating, the schedule and project risks. Just as the baseline.

Is This Answer Correct ?    0 Yes 0 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / surender yadav

The Partial blocks of achievement is a milestone.
Particulary for projects more than of 6 months period If
percieved due to constraint -Technology Change , fresh
demand from customer(changing the SOW),products becoming
obsolete there can be mutual negotitation to change the
milestone dates (some times penalty may be leivied) and the
goal.

Is This Answer Correct ?    2 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / amarnath

It is a process which must be carried out during the
project Management or to be planned during the project
planning stage to list the actions to be taken in case of
any requirement changes arises. This term is used while
communicating with the stakeholders. For example, “If there
are any changes in the system requirements we need to
Readjust the goal and milestones” and if the stakeholders
ask, we should be able to list the planed steps for the
process, which depends on the project in hand.

Is This Answer Correct ?    1 Yes 2 No

Post New Answer

More Project Management Interview Questions

You have accumulated project information throughout the project and need to distribute some important information you just received. All of the following are part of information distribution methods except; A. Electronic mail B. Videoconferencing C. Electronic databases D. Voice mail

0 Answers  


Common causes of variances are a result of all of the following except: A. Random variances B. Predictable variances C. Special variances D. Variances that are always present in the process

0 Answers  


Why do you want to switch over from IT to management?

0 Answers   EX,


You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope. Which of the following is true? A. Project scope changes do not require CCB approval. B. Performance measurement baselines are affected by scope changes. C. Project scope change uses inspection to determine if change has occurred. D. Project scope change uses workarounds to correct unexpected problems with scope change.

0 Answers  


All of the following are true regarding the ADM method except: A. It's a tool and technique of Activity Sequencing. B. It uses one time estimate to determine durations. C. It's also called AOA. D. It's rarely used today.

0 Answers  






Which of the following describes the Executing process? A. Project plans are put into action. B. Project performance measurements are taken and analyzed. C. Project plans are developed. D. Project plans are published.

0 Answers  


During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.

0 Answers  


Which of the following is true regarding constraints and assumptions? A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes. B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team. C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project teamwork within predefined budgets or time lines. D. Constraints and assumptions are inputs to the Initiation process. They should be documented, as they will be used throughout the project Planning process.

0 Answers  


Describe size oriented metrics.

0 Answers  


The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration

0 Answers  


You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery score chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PD technique. You know that: A. PDM uses AON diagramming methods. B. PDM uses AOA diagramming methods. C. PDM uses ADM diagramming methods. D. PDM uses PDM diagramming methods.

0 Answers  


What is the key activity during Contract Closeout and Administrative Closure? A. Documenting lessons learned B. Creating project archives C. Disseminating information to formalize project closure D. Documenting project closure

0 Answers  