All of the following are tools and techniques of the Performance Reporting process except:
A. Variance analysis
B. Performance reporting
C. Information distribution
D. Performance reviews
No Answer is Posted For this Question
Be the First to Post Answer
You are the project manager for Insomniacs International. Since you don't sleep much, you get a lot of project work done. You're considering recommending a project that costs $575,000, and expected inflows are $25,000 per quarter for the first 2 years, and then $75,000 per quarter thereafter. What is the payback period? A. 40 months B. 38 months C. 39 months D. 41 months
What are the different software reengineering activities?
You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.
The outputs of the Administrative Closure process include all of the following except: A. Project archives B. Project closure C. Lessons learned D. Formal acceptance
You work for a large manufacturing plant. You're in the Initiation process of a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take? A. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend the project proceed. B. The project manager should document the project's goals and known deliverables in a high-level overview document and assume the project is a go. C. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend a feasibility study be performed. D. The project manager should document the project's goals and known deliverables in a high-level overview document and deliver it to the stakeholders.
You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
The project manager has the greatest influence over quality during which process? A. Quality Planning B. Quality Assurance C. Quality Control D. Quality Change Control
Your project got delayed by 40 days and you have to keep it back.what steps you would take.
What is the difference between project, program, and portfolio?
Your project has recently experienced change. Some of the agreed-upon WBS elements have been changed as a result. What kind of change has occurred? A. Schedule change B. Risk response change C. Quality change D. Scope change
what is software project planning?
Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.