What is "Readjustig goal and Milestone" in project
managment and project planing

Answer Posted / tushar waghode

Re-adjusting goals can be viewed as a part of change
management where impact of changes result in change of
scope of the deliverables or project.
Milestone is used as a checkpoint at logical points in a
schedule to ascertain completeness of work at that point.
In Microsoft project a milestone is a zero duration, zero
resource intentive activity.

Is This Answer Correct ?    25 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How do you ensure that your project is always on track?

503


Explain the difference between Project management and IT management.

615


Which of the following is true regarding schedule variances? A. They impact scope, which impacts the schedule B. They sometimes impact the schedule C. They always impact the schedule D. They never impact the schedule

608


Which of the following describes the Executing process? A. Project plans are put into action. B. Project performance measurements are taken and analyzed. C. Project plans are developed. D. Project plans are published.

528


You are the project manger for Xylophone Phonics. They produce children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on? A. Resource Planning B. Organizational Planning C. Staff Acquisition D. Human Resource Acquisition

571






All of the following are true regarding configuration management except: A. Requires all acceptance decisions to be made through the CCB B. Serves as a change control system C. Describes the physical characteristics of the product of the project D. Controls changes to the characteristics of an item or system

671


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

607


All of the following arc tools and techniques of the Project Plan execution process except: A. Project management information system B. Work authorization system C. Organizational policies D. General management skills

547


What is tracing process? How this can be enabled?

573


You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following? A. Using the previous project's alternatives identification as a template B. Reusing the previous project's benefit/cost analysis as justification for this project C. Using the previous project's WBS as a template D. Reusing the previous project's product description when writing the scope statement

615


You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What is the CPI of this project? A. 0.80 B. 1.25 C. 1.5 D. 0.83

612


You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true? A. This project ended due to starvation because the funding was cut off B. This project ended due to integration because the resources were distributed elsewhere C. This project ended due to starvation because the resources were distributed elsewhere D. This project ended due to integration because the funding was cut off

753


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any time during the day. You need to purchase an expensive piece of hardware as part of this project. One of the vendors bidding on the project is a close friend. In order to win the bid, she needs to know how much money the company is willing to spend on the equipment and consulting. Your friend asks you to give her this confidential information and not tell anyone you did. Which of the following is the most appropriate response? A. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it's a conflict of interest. B. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it’s a personal gain. C. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s a conflict of interest. D. Tell your friend that as a PMP, you’re required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s an ethics violation.

637


Your company, Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. You are ready to create the WBS. Which of the following is true? A. The WBS should include the three new products and the advertising campaign as level two deliverables. B. The WBS should include the three new products as level two deliverables. C. The WBS should include the three new products as level two deliverables and the advertising campaign as a level three deliverable. D. The WBS should include the three new products and the advertising campaign as level three deliverables.

647


Your company manufactures small kitchen appliances. They are introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. In order to determine the characteristics and features of the new product line, you will have to perform which of the following? A. Fast tracking B. Consulting with the stakeholders C. Planning the project life cycle D. Progressive elaboration

746