As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. Part of your responsibility concerns applying professional knowledge. All of the following are part of applying professional knowledge except:
A. Developing relationships based on mutual respect
B. Staying abreast of project management practices
C. Keeping up with industry trends and new technology
D. Honestly reporting your project management experience
No Answer is Posted For this Question
Be the First to Post Answer
What are the Scope Planning process tools and techniques? A. Benefit/cost analysis, work breakdown structure templates, expert judgment, and supporting detail B. Product analysis, benefit/cost analysis, alternatives identification, and expert judgment C. Product analysis, work breakdown structure templates, supporting detail, and expert judgment D. Benefit/cost analysis, alternatives identification, supporting detail, and expert judgment
You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure does this represent? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization
Your project involves the research and development of a new food additive. You’re ready to release the product to your customer when you discover that a minor reaction might occur in people with certain conditions. The reactions to date have been very minor, and no known long-lasting side effects have been noted. As project manager you should: A. Do nothing because the reactions are so minor that very few people will be affected. B. Inform the customer that you've discovered this condition and tell them you'll research it further to determine the impacts. C. Inform your customer that there is no problem with the additive release the product to them. D. Tell the customer you'll correct the reaction problems in the next batch but you'll release the first batch of product to them now to begin using.
Sally is a project manager working on the Resource Planning process. She should consider all of the following when developing the resource requirements output except: A. WBS B. Supply purchase policies C. Resource rates D. Special knowledge and talents
You are a project manager working on contract with a company in a foreign country. At the project kick-off meeting, you are given an expensive-looking gift. The person who presented this to you said that it is customary in their country to give their business partners gifts. What is the most appropriate response? A. Thank them and decline. Explain that this is considered personal gain, which is unacceptable in your country. B. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. C. Thank them and decline. Explain that this is considered a conflict of interest, which is unacceptable in your country. D. Thank them and accept since you know that it would be considered offensive to decline the gift in their culture. Immediately report the acceptance of the gift to the appropriate parties at your company so that your actions are not called into question later.
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail score for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity. What is the most appropriate response? A. You decline to participate in the initial meetings with the foreign business partners due to conflict of interest. B. You've not yet received an official offer from the competing company for your new job opportunity, so you choose to participate in the initial meetings with the foreign business partners. C. You decide to participate in the initial meetings with the foreign business partners because any information you gain now will help you when you make the move to the new company. D. You inform the foreign business partners that you're going to be working with a new company and that you know the deal they'll receive from the competing company is better than the one this company is proposing.
This measurement is the value of the work that's been completed to date: A. PV B. AC C. EV D. EAC
The tools and techniques of Source Selection include all of the following except: A. Contract negotiation B. Work authorization system C. Weighting systems D. Independent estimates
The Project Integration Management knowledge area is made up of which of the following processes? A. Initiation, Project Plan Development, and Integrated Change Control B. Project Plan Development, Project Plan Execution, and Integrated. C. Project Plan Development, Initiation, and Scope Planning D. Initiation, Scope Planning, and Integrated Change Control
You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope as the glitch changed the characteristics of the product. Which of the following is true? A. Changes to product scope are reflected in the project scope. B. Changes to product scope are reflected in the integrated change control plan. C. Changes to product scope are a result of changes to the product description. D. Changes to product scope are a result of corrective action.
Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.