Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


define the zero date in project management

Answers were Sorted based on User's Feedback



define the zero date in project management..

Answer / parish

the project start date after complete approval from
technical ,financial and regilatory agency.This is called
zero date of project.

Is This Answer Correct ?    43 Yes 10 No

define the zero date in project management..

Answer / satish

The zero date of a project signals the effective start of
the project. It is an important part of the project planning
and establishment. The completion of projection will be
counted from this point of time. It is important to ensure
that all activities that effect project performance like
arrangement of finance, infrastructure facilities, formation
of new company, division, government and clearance etc.
beside time, cost and technical parameters are fully dealt
/designed / established / started by this time.

Is This Answer Correct ?    30 Yes 5 No

define the zero date in project management..

Answer / ashok

Zero date is the effective start date of the project. Usually it is the date of LOI / Contract signing date. Duration of the project is calculated on basis of this date.

Is This Answer Correct ?    9 Yes 3 No

define the zero date in project management..

Answer / abdulrahman

Zero date is milestone.

Is This Answer Correct ?    13 Yes 9 No

define the zero date in project management..

Answer / chellaiah

Zero date is the project start date.

Is This Answer Correct ?    5 Yes 5 No

define the zero date in project management..

Answer / a.barakat

zero date : is the identified date for the start of the project

Is This Answer Correct ?    1 Yes 1 No

define the zero date in project management..

Answer / sarat

In a Power Plant Project, the date on which a contract document is signed with the EPC contractor for BTG Package is considered as a Zero Date

Is This Answer Correct ?    2 Yes 2 No

define the zero date in project management..

Answer / anoop kumar

If the activity of the project is not on the critical path.
The activity is called as zero date. WHich actually means
no schedule and effort varince in to the project.

Is This Answer Correct ?    21 Yes 35 No

Post New Answer

More Project Management Interview Questions

All of the following are true regarding Ishikawa diagrams in the Quality Planning process except: A. They are also called cause-and-effect diagrams. B. They are also called fishbone diagrams. C. They are a tool and technique of this process. D. They are an output of this process.

0 Answers  


What was the biggest challenge you faced in your project?

1 Answers   HCL,


Project managers use this conflict resolution technique most often: A. Smoothing B. Confronting C. Naming D. Forcing

0 Answers  


What are the outputs of the Scope Planning process? A. Product analysis, scope statement, and scope management plan B. Scope statement, scope management plan, and WBS C. Scope statement, supporting detail, and WBS D. Scope statement, supporting detail, and scope management plan

0 Answers  


Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  


You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.

0 Answers  


You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true? A. This project ended due to starvation because the funding was cut off B. This project ended due to integration because the resources were distributed elsewhere C. This project ended due to starvation because the resources were distributed elsewhere D. This project ended due to integration because the funding was cut off

0 Answers  


Project selection criteria might include: A. Benefit measurement methods B. Constrained optimization analysis C. NPV calculations D. Potential market share or increased public perception

0 Answers  


You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written

0 Answers  


You have just prepared an RFP for release. Your project involves a substantial amount of contract work detailed in the RFP. Your favorite vendor drops by and offers to give you and your spouse the use of their company condo for your upcoming vacation. It's located in a beautiful resort community that happens to be one of your favorite places to go for a get away. What is the most appropriate response? A. Thank the vendor but decline the offer, as you know this could be considered a conflict of interest. B. Thank the vendor and accept. This vendor is always offering you incentives like this, so this offer does not likely have anything to do with the recent RFP release. C. Thank the vendor, accept the offer, and immediately tell your project sponsor so they're aware of what you're doing. D. Thank the vendor but decline the offer because you've already made another arrangement for this vacation. Ask them if you can take a rain check and arrange another time to use the condo.

0 Answers  


What are the qualities of a good project manager?

0 Answers  


Categories