Answer / geek
You can do all of the following on the Work Order-less
Completions window:
-Complete unscheduled or scheduled assemblies to Inventory
-Return unscheduled or scheduled assemblies from Inventory
-Scrap assemblies from and return scrapped assemblies to any
operation
-Explode the assembly's bill of material and add, delete,
and change components-and review items under lot and serial
number control
-Specify lot, serial, and lot and serial information for
assemblies and components.
-Create material reservations for assemblies that are linked
to sales orders
-Replenish production kanbans
| Is This Answer Correct ? | 5 Yes | 0 No |
Answer / mohan
Work order less completion in WIP helps us to complete the
job manually without creating a job.
example.
Suppose client wants to continue a job creation function in
other ERP like peoplesoft,SAP but they wants to track
inventory in Oracle apps at that we used to go for Work
order less completion.
| Is This Answer Correct ? | 4 Yes | 0 No |
What is the use of display option in Routing and Bill of Material.(e.g Current, Current and Future) and Checked Implemented.
What do you mean by Planning Item?
If i want to map a organization structure, where i hv 1 operating unit that is looking after only purchasing and payables activities, whereas another operating unit is looking after OM as well as receivables. I hv one more warehouse or say plant, where i am manufacturing & despatching the goods. Wiil it be solved by setting up purchasing at one OU and OM at another OU. Do I need to perform any additional setups? Please Suggest.
Types of Calendar? where we are define it?
What all diffrent typw of resources are there?
what are reference designators and how they are used practically .Please site few examples.
What setups are done in WIP?
What is yield point?
what are the Nine mandatory Flexi fields in Inventory set up
What to mean by Multi Org? what are all the multi org setups?
What is Reorder point and Reorder quantity? and what is its significance?
I got my new offer as Functional consultant in Oracle Apps. Now i m having only domain knowledge ( SCM ). Will anybody explains briefly abt the Manufacturing process in Oracle Apps ??