how can calculate material in 1:1.5:3 ratio in concrete
Answer / madhusudhan
for 1 m³ concrete (M20=1:1.5:3)the material required is
(1+1.5+3)=5.5
1/5.5=0.1818*1440=261kg cement or 5.32 bags
1.5/5.5=0.272 m³ Fine aggregate
3/5.5=0.545 m³ Coarse Aggregate
| Is This Answer Correct ? | 0 Yes | 0 No |
Tell me about triple point of water.
cement quantity in 1 M3 pcc
what is the allowable silt % in river sand for Dam concreting.
what is the IS code no. for concrete wastage?
What are the applications of cad?
What is difference between combin footing & rapt footing
what is the out turn of one masson in plastering, masonary work in 8 hours, with limited healper? what is the out turn of corpender in form work? wood work? in 8 hour with limited healper? what is the out turn of bar bendarin 8 hour with limited healper for slabs, beams, coloumn?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
how to identify np3 pipe and np4 pipe
0 Answers NCC, Petron ltd, RCC Laboratories India Private Limited,
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
From which end do you start deshuttering in a) cantilever portion b) simply supported portion
how much % of cement can be replaced by flyash ....
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)