Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how can calculate material in 1:1.5:3 ratio in concrete



how can calculate material in 1:1.5:3 ratio in concrete..

Answer / madhusudhan

for 1 m³ concrete (M20=1:1.5:3)the material required is
(1+1.5+3)=5.5
1/5.5=0.1818*1440=261kg cement or 5.32 bags
1.5/5.5=0.272 m³ Fine aggregate
3/5.5=0.545 m³ Coarse Aggregate

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

Tell me about triple point of water.

0 Answers   Bechtel,


cement quantity in 1 M3 pcc

2 Answers  


what is the allowable silt % in river sand for Dam concreting.

3 Answers  


what is the IS code no. for concrete wastage?

0 Answers  


What are the applications of cad?

0 Answers  


What is difference between combin footing & rapt footing

0 Answers  


what is the out turn of one masson in plastering, masonary work in 8 hours, with limited healper? what is the out turn of corpender in form work? wood work? in 8 hour with limited healper? what is the out turn of bar bendarin 8 hour with limited healper for slabs, beams, coloumn?

2 Answers  


how to take the quantity of block work and plastering  1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate

0 Answers  


how to identify np3 pipe and np4 pipe

0 Answers   NCC, Petron ltd, RCC Laboratories India Private Limited,


How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.

0 Answers  


From which end do you start deshuttering in a) cantilever portion b) simply supported portion

3 Answers   ITC Infotech,


how much % of cement can be replaced by flyash ....

4 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)