Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how many cement bags required for one cum of brick work the brick size is 20x10x10.



how many cement bags required for one cum of brick work the brick size is 20x10x10...

Answer / milind borkar

It is depends on what is a proportion of cement : sand .

Mortar proportion 1:4 or 1:6.

For example :- for 1:4 proportion 1.90 bags and for 1:6 proportion 1.25 bags

Is This Answer Correct ?    13 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

give an example for cantilever structure

9 Answers  


how to calculate result on Plate bearing test?

1 Answers  


please describe clear cover in column from stirups to face

5 Answers  


crank types

0 Answers   MNC, RBDC,


how many cement bags required for one cum of brick work the brick size is 20x10x10.

1 Answers   Casa Grande,


why construction joint in the slab should be l/3 of span? what's the technical reason for that?

1 Answers  


if 6.0M x3.0M Boat floating on water One person Sit on Boat Then the boat Sink about 15cm .Then what is the wt of person.

3 Answers  


what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix

1 Answers  


Can anybody please tell the procedure to calculate the quantity of admixture in Self Compacted COncrete??

2 Answers  


What is the diff. Between rectangle & parallelogram?

10 Answers  


What is the mixing of D.P.C?

3 Answers  


relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2

1 Answers   Infosys, SSC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)