Answer / koshik
Brick work :-7to10 days
All concreting:-14to20days
Is This Answer Correct ? | 11 Yes | 0 No |
Answer / dileep naik
It is depending upon weather condition.
Generally Brick & concrete work cured atleast 7days.
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / abdul aziz
Concrete 7 day 21 days depend on weather or no need curing use thermal blanket for self curing or curing compound chemicals
Is This Answer Correct ? | 0 Yes | 0 No |
What is Curtailing of R/F
How to calculate the steel for 392c.meter*450c.meter rcc slab
Name the standard sand for concrete tests
how to convert m 25 concrete to m 40?
What is the IS code of Rcc & PCC
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
how to calculate the cement, sand, coarse aggregate required for one cubic meter of concrete?
how to calculate load for a bungalow and 1column carry how much load if the size of column ,9"*15" .....or total structure load......
what is high type road and low type roads
Define What is the meaning of a blue land surveyors flag?
state the difference between direct and indirect cold water supply scheme