Brick work how many days curing and at any concreting pl
Answer Posted / dileep naik
It is depending upon weather condition.
Generally Brick & concrete work cured atleast 7days.
| Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?
How do You Maintain a structure after getting cube test of low strength.
how to absorb to site basic corrections? which are the important correction?
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
What is meant by Crystal Concrete?
how to calculate the concrete mix m30 by volume
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
Define What happens to Load at yielding ?
Difference between lime, distemper and plastic emulsion?
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
Which is the most prominent tower of world?
what is the mix design for M:60 with micro silica andmetakaoline?
which type of instrument included in plumbing work?name of instrument?
How to check slab shuttering level.? Or check list for slab ?