whike making bbs we deduct 2d for every bend in bar but theoretically we cant subtract 2d for every bend and for every dia of bar , so plz tell me the exact deduction for bends for different dia of bars and for different angles ??
Answer / jonah
2d is correct increase but during subtraction 1d is to be subtracted as the increase in dia is for one bend.
| Is This Answer Correct ? | 1 Yes | 1 No |
why distibuters used in rcc slsb
how can we calculate the amount of concrete in trapezoidal footing?
how to placeing reinforcement in slab?
Respected sir i am appearing for the exam this year.I will be highly obliged if u kindly send me last year's interview paper on civil engineering in my email address debosmitroy@yahoo.in
How to calculate the Volume of PCC, Footing Base, Footing Column, Grouting, Base Plat and plinth beam
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
cement constant for brick works
What is the minimum depth of a slab?
How to check Diameter of Np2 rcc pipe?
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
What is the maximum allowable wastage in pouring of Ready Mix Concrete received at location with transit mixtures. Work scope includes both Direct Pouring & manual pouring.
1 Answers AKM Construction Management,
how many nails in 1 kg for 1 inches?
2 Answers Jagson, Shoba Devlopers, Sobha Developers,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)