Answer / noman saeed
Bleeding of concrete means the separation of cement slurry from the concrete mass.Usually this paste comes on the top of the concrete surface or leaks through the pores in the form work.
| Is This Answer Correct ? | 22 Yes | 2 No |
Answer / javed dawar
Bleeding of concrete occur due to excess of water ,by the excess of water the cementious material wash out. and due to this concrete lost their strength.
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / mohit jain
bleeding is a form of segregation in which water tends to rise to the surface of freshly placed concrete. causes of bleeding of concrete are
high water content
poor mixing skills
| Is This Answer Correct ? | 3 Yes | 0 No |
What is the origin of name railway sleepers?
what would be compressive strength of cube for 7 days if design mix of M15
What Are The Different Type Of Slump Test Indications?
How to convert 0.44 N/MM2 in to Kgf/cm2
2 Answers Ukay Metal Industries,
What is special features of RGS Rebar detaling software?
what will be the difference in compressive test results for a 150 mm cube, a 150 mm cylinder and a 300 mm cube
what is the material consumption of 1:2:4 by kilogram?
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
0 Answers College School Exams Tests,
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
what will be the quantity of matterial and water for pcc in 1 cubic meter , the ratio is 1:4:8 (cement:sand:aggr) ?
Are you interested in starting a fly ash brick making unit?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)