Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what are the steps of syncronizing the generator with an infinite grid?

Answers were Sorted based on User's Feedback



what are the steps of syncronizing the generator with an infinite grid?..

Answer / bhanu

first of all you have to match the generator voltage & frequency with grid then you can synchronise

Is This Answer Correct ?    13 Yes 0 No

what are the steps of syncronizing the generator with an infinite grid?..

Answer / npti.pe

1st match the voltage and freq of gen. and grid, then using a synchro-scope match the phase while closing the GCB

Is This Answer Correct ?    6 Yes 0 No

what are the steps of syncronizing the generator with an infinite grid?..

Answer / sarang

we have match our voltage freq. and phase angles with the grid values only then we synch,

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Power Plant Engineering Interview Questions

transformer shut down process.

0 Answers  


what is the formula for converting mmwc to tph in a dp type transmitter.what is the range in plc(in tph) if dp tx.range from 0 to 5000mmwc.

2 Answers   CCC, Korba Power Plant, Shyam Steel, Utkal Alumina International,


what is natural frequency of turbine shaft .

0 Answers   Thermax,


can dp type level transmitter work in under vaccum condition

0 Answers  


LAPT working in alternator / generator

0 Answers   Power Plant,


Difference between islanding and house load operation.

2 Answers  


What is tripping relation between the turbine exhaust pressure and turbine last stage pressure....???

1 Answers   Jaypee,


why HT motor star not grounded?

4 Answers   Apollo,


63.5 ohm NGR is connected with our gas engine genrator running at 500 rpm, 50 hz and synched with WAPDA at 6.3 KV bus voltages, 2500A and 25KA(1 sec). can some one give me proper calculations how it comes 63.5ohm?????

2 Answers   UET,


What happens if air is present in LPH and HPH.

2 Answers  


What should be the neutral and body grounding sysytem for grid (132 KV) parallel generators (440 volts)?

1 Answers   Rahimafrooz,


What is difference between secondary Air & Tertiary Air and Their use.?

0 Answers   Bhel,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)