what is the condition of transformer parallel operation ?
Answers were Sorted based on User's Feedback
Answer / prafulkumar
the vector group should be match(phase angle)
voltage rating should be same
frequency should be match
Is This Answer Correct ? | 15 Yes | 0 No |
Answer / rakesh. a.d
Two transformers terminal voltage should be same
Two transformers impedances should be same
Is This Answer Correct ? | 8 Yes | 4 No |
Answer / medroua
Mandatory conditions:
Same phase angle shift, Same polarity, Same phase sequence and same frequency.
Convenient conditions:
Same voltage ratio & Turns Ratio, Same Percentage Impedance, Same KVA Rating, Same Position of Tap changer if any.
Is This Answer Correct ? | 2 Yes | 0 No |
Why attemperation is required in HRSG in a combined cycle power plant?
explain(why) with circuit for pick up of restricted earth fault protection due to external fault
can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525
what is the formula for converting mmwc to tph in a dp type transmitter.what is the range in plc(in tph) if dp tx.range from 0 to 5000mmwc.
2 Answers CCC, Korba Power Plant, Shyam Steel, Utkal Alumina International,
LAPT working in alternator / generator
how to differentiate between "ALL fuel lost" and "All Flame Lost" in Boiler MFT condition?
Where is the pressure reduce valve in the power plant
what is the perfect location for furnace draft transmitter in AFBC boiler?
what is need of primary water system in power plant?
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
Is it not bad to bleed steam from turbine stages before utilizing its energy.
I am opertaing generators which are beyond 14000hrs and now the fuel consumption is about 2kw per liter of diesel. The engines are due for overhauling. is this normal