How to calculate material requirement for 230mm thick, 1 sq.m
brick masonry?
Answers were Sorted based on User's Feedback
Answer / selva kumar j
TOTAL VOLUME OF BW IN CM 1:6= 1*.23=0.046 M3
BRICK REQUIRED - 11 5NOS
CEMENT REQUIRED - 11 KGS
SAND REQUIRED - 0.046 M3
Is This Answer Correct ? | 11 Yes | 5 No |
Answer / rohit dhingra
volume of mix = 1x0.23 = 0.23 cum
no. of bricks = 0.23x500 = 115 Nos
as for mortar ratio is 1:6 assumed.
cement require = 1.25x0.23=0.2875 bag or say 14 kg cement
sand require = 0.23x0.23=0.052 cum
Is This Answer Correct ? | 4 Yes | 2 No |
1)define the critical items in rcc framed G+18 bldg. as Cr Activity 1,Cr Activity 2,Cr Activity 3...etc. 2)on what logic is MSP and Primavera planning based.FS SF FF...
for basic costing, how can we calculate how much amount of steel and cocrete will go in per sqft? and what are the thumbrules?
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
Should column area deducted from form work measurement of slab in building?
HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL
how to calculate steel for beam of simple home and for heavy buliding ? explain me briefly
what is poissons ration of steel?
What are the standard plastic limit/liquid limit/plasticityindex for differrent type of soils?
what is the labour requirement for solid & hollow block work
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
States some of the commonly used commands in cad software’s?
how can u extent the final setting time of cement?
3 Answers TNPSC Tamil Nadu Public Service Commission,