what is commissioning & pre commissioning , explain with
difination
Answers were Sorted based on User's Feedback
Answer / kalpesh g patel
Commissioning is the process of assuring that all systems and components of a building or industrial plant are designed, installed, tested, operated, and maintained according to the operational requirements of the owner or final client. A commissioning process may be applied not only to new projects but also to existing units and systems subject to expansion, renovation or revamping.
In practice, the commissioning process comprises the integrated application of a set of engineering techniques and procedure to check, inspect and test every operational component of the project, from individual function, such as instrument and equipment, up to complex amalgamations such as modules, subsystems and systems.
Commissioning activities, in the broader sense, are applicable to all phases of the project, from the basic and detailed design, procurement, construction and assembly, until the final handover of the unit to the owner, including sometimes an assisted operation phase.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / kalpesh g patel
Commissioning is the start up of the equipment for the first time. It is when you run the equipment and carry out tests to verify it is running as intended i.e. to design specifications. Commissioning tests are normally run against a design data baseline. Commissioning also includes things like checking oil levels, fluid levels, temperatures, pressures and for general issues that are contradictory to the intended correct operation of the equipment.
| Is This Answer Correct ? | 0 Yes | 0 No |
Is it ok, to use non-contact type Radar type LT, on a tank that is half circular from the bottom side? If yes the, isn't the waves gonna bent in other directions?
0 Answers Process Control Technologies,
I HAVE GOT TYPICAL PROBLEM WITH THE TEMP.INDICATION. THE PROBLEM IS THE K-TYPE T/COUPLE OUT PUT IS CONNECTED TO A INDICATOR.THE INDICATION FLUCTUATES SOME TIMES AND SOME TIME IT IS STABLE. WHEN I CHECKED OUT PUT OF T/COUPLE THE MV WILL NOT VARY. WHERE AS INDICATION FLUCTUATES. WHEN I GIVE MV SOURCE TO T/COUPLE EXTENSIONCABLE FROM THE FIELD IT INDICATION IS STABLE. WHEN GIVE MV SORCE TO INDICATOR ITS INDICATION IS STABLE. PLEASE CLARIFY.
which types of oxygen analyzer describe with drawing ?
Can we used Condensate Pot on flow transmitter which is using on liquid having sluge and DP transmitter is in pit and below the process line,Can we used Condensate pot for accamulate the Sluge?
how many type conductivity sensor ?
what is the tempareture conpensation?what is the use of this?
Tell me about PID Tuning and what is PID.
What is the difference between ROM & RAM .
What kind of feedback is used in DP cells.
How to calibrate H2s Dectector
What is the formula to convert mv to temperature in k type thermocouple?pls simply elaborate? I got one ans.it is Temp=mv×25°+atmospheric temp,but here what is 25°,i confusef ,so pls????
please give me combustion cntrl interlock details? if possidle drawing also?for this one is there any website ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)