Commissioning is the process of assuring that all systems and components of a building or industrial plant are designed, installed, tested, operated, and maintained according to the operational requirements of the owner or final client. A commissioning process may be applied not only to new projects but also to existing units and systems subject to expansion, renovation or revamping.
In practice, the commissioning process comprises the integrated application of a set of engineering techniques and procedure to check, inspect and test every operational component of the project, from individual function, such as instrument and equipment, up to complex amalgamations such as modules, subsystems and systems.
Commissioning activities, in the broader sense, are applicable to all phases of the project, from the basic and detailed design, procurement, construction and assembly, until the final handover of the unit to the owner, including sometimes an assisted operation phase.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / kalpesh g patel
Commissioning is the start up of the equipment for the first time. It is when you run the equipment and carry out tests to verify it is running as intended i.e. to design specifications. Commissioning tests are normally run against a design data baseline. Commissioning also includes things like checking oil levels, fluid levels, temperatures, pressures and for general issues that are contradictory to the intended correct operation of the equipment.
| Is This Answer Correct ? | 0 Yes | 0 No |
what is the way of measuring air flow in air duct?explaim instruments used and DP creation in line?
what are the following documents comes under loopchecking
difference between transducer and converter in instrumentation
There are many type of control cable like pair,core,tried, What are defination each one
Pressure transmitter working Principles?
why we use only 4 to 20ma other than 0 to 16 ma
hi! i want to know about mpse exam.
how to check the leak in thermowells
how the presure switches are calibrated? and what happen inside?
how bolometer is used in temperature measurement ??
what is the dp across a orifice plate & how much is permanent pressure across an orifice plate.
what is the exact job for automation enggineer?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)