Extra rod should be provided for beam in two section
(i.e) compression zone & Tension zone.*It depending on the size of beam*.
In compression zone , the extra rod should be provided on compression zone of the beam and extent up to one-third of beam's clear span both side of support....
In tension Zone, provide extra bottom bar in the middle of beam's bottom portion.
| Is This Answer Correct ? | 15 Yes | 4 No |
What is Refuse Area In High Rise Building ?
which size of box use of cement,sand,aggregate to use the m 20 concrete. i know the quantity of material cement 400 kg or 8 beg ,662 kg sand and 1200 kg aggregate. i can use only 1 beg cement so pls give me answer . thx in advance
How is rate analysis prepared for M 25 grade of concrete?
what is mixed design, define it? what is way beecher?
For 100 bag cement how i will calculate sand and metal aggregate.Mixing proportion 1:1.49:2.38
How to do base isolation using ETABS software?
How is improve my knowledge in construction industries....
why construction joint in the slab should be l/3 of span? what's the technical reason for that?
I have to conduct load test on greting cover, pressure gauge is in kg cm2, how to caluculate load on this greting cover.
how to take concrete quantity for precast segment for viaduct project?
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
what is escalation?how it is done?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)