Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how to calculate the loads on slab? what are the steps?



how to calculate the loads on slab? what are the steps? ..

Answer / abdul tawaf khan

1) Dead load of slab = 1 * 1 * 25 * D
2) Live load of slab = 1 * 1 * Live load intensity as per IS specifaction
3) Finishing load = 1 * 1 * 24 * t
Where , D = overall depth of slab
t = thickness of floor finish
Also condier Wind load, if any case.

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is meant by Stagging?

3 Answers   Alembic, Shirke,


why spacer in reinforcement? 

3 Answers   ECCI,


which"s we should use for concrete ppc or opc?

9 Answers   Wipro,


2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32

0 Answers  


it is a corrected question." make a list of engineering property(properties) of soil.

0 Answers   AAI Airports Authority Of India, DLF,


i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............

0 Answers   Ecil,


what is the lap length

2 Answers   Access Design,


What are the common ways of demolition?

0 Answers  


how to mack bbs

1 Answers  


What is the method of soil replacement test?

0 Answers  


if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel

0 Answers  


how much anti termite treatment( ATT) liter used in one sq mtr floar area? & what is ratio of ATT & water.

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)